Construction contract conditions
Contract conditions set out the principal legal relationship between the parties to a construction project, determining the allocation of risk and consequently, price.
English law, unlike the codified legal systems in Europe which recognise a duty of good faith, is not concerned with fairness but with certainty (unless it is a consumer contract protected by statute such as the Consumer Protection Act 1987 or the Unfair Contract Terms Act 1977).
The construction sector has a wide range of standard forms of contract which are intended to balance the risk of the parties but more importantly, through extensive and repeated use, give rise to a certainty of meaning. Well-known standard form contracts include the Joint Contracts Tribunal (JCT), the New Engineering Contract (NEC) and for international projects Fédération Internationale des Ingénieurs-Conseil (FIDIC).
See the article on Contracts for more information.
Standard form contracts also provide for different procurement routes, such as:
- Construction management.
- Design and build.
- Design build finance and operate (PPP / PFI / DBO / BOOT).
- Emerging cost contracts.
- Engineering Procurement and Construction Contract (EPC) / Turnkey contract
- Engineering Procurement and Construction Management contract (EPCM)
- Furniture, Fixtures and Equipment contract (FF&E).
- Framework agreements.
- Management contract.
- Measured term contracts
- Measurement contract ('re-measurement' or ‘measure and value’ contract)
- Partnering.
- Prime cost contract / cost plus contract / cost reimbursable contract
- Prime contracting / prime-type contracting
- Traditional contract.
See the article on Procurement routes for more information.
Typical conditions found in construction contracts can include (in alphabetical order):
- Access to the construction site.
- Assignment, rights of third parties and collateral warranties.
- Commissioning.
- Contractor's design.
- Contract sum and adjustment,
- Date for possession, deferment of possession, progress, delays, completion date, suspension of works and termination.
- Dispute resolution procedures and alternative dispute resolution.
- Employer's instructions.
- Force majeure.
- Information release schedule.
- Insolvency.
- Injury, damage and insurance.
- Joint Fire Code.
- Liquidated damages.
- Net contribution clause.
- Partial possession.
- Payment, valuation (including off-site materials), certificates, fluctuations and retention.
- Practical completion.
- Project management and contract administration.
- Quality of works.
- Relevant events (compensation events), extensions of time and loss and expense.
- Sectional completion.
- Statutory obligations.
- Sub-contractors.
- Testing and defects (defects liability period)
- Variations, prime cost sums and provisional sums.
Conditions of contract must be read in conjunction with specification documents, drawings bills of quantities, activity schedules and special conditions. Standard form contracts often comprise suites of contracts with ‘back to back’ subcontracts, consultant appointments and collateral warranties. The use of core conditions with option schedules or supplemental provisions is also now common (see NEC contract).
[edit] Related articles on Designing Buildings
- Addendum.
- Alternative dispute resolution.
- Articles of agreement.
- Common law.
- Competitive procedure with negotiation.
- Condition.
- Construction contract.
- Construction law.
- Contract administrator.
- Contract negotiations.
- Contract strategy.
- Contractual right.
- Delay damages.
- Disallowed cost.
- Escalation.
- Essentials of a contract.
- Excepted risk.
- Extension of time.
- Form of tender.
- Hybrid construction contract.
- Key dates.
- Liquidated damages.
- Loss and expense.
- Modifying clauses in standard forms of contract.
- Named specialist work.
- Negotiated Procedure without Prior Publication NPwPP.
- Outturn cost.
- Payment for extra work.
- Pre-contract management.
- Proprietary information.
- Quantum meruit.
- Right to payment.
- Supply chain management.
- Variation.
- Z clauses.
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Comments
this site is indeed very informative👍 worth to spend sometime reading during work break