Back-to-back provisions in construction contacts
The term ‘back-to-back’ refers to the replication of contractual terms through the supply chain.
As contractors increasingly sub-contract much of their work to others, so the construction supply chain has become longer and more complex. It is important for all parties to ensure that certain rights and obligations exist not only in their own agreements, but also in the agreements contracting parties have with others. This ensures that the main contractor is not left responsible for all obligations to the employer, that sub-contractors have enforceable rights and that timings are co-ordinated throughout the supply chain.
Typically, descriptions of back-to-back requirements focus on the relationship between the employer, contractor and sub-contractors, but they apply equally to sub-sub-contractors, suppliers, consultants and sub-consultants.
In its strictest form, back-to-back refers not just to the replication of contractual rights and obligations in different levels of contract, but to a requirement that the terms of agreement at one level are included in agreements at lower levels.
This is a very complex process that requires careful consideration and drafting to ensure the correct terms - and only those terms - are passed on, that they are phrased appropriately and that requirements, and in particular timings, are properly co-ordinated.
Back-to-back provisions can be created by:
- Including reference to terms in the main contract to be included, excluded or varied in a sub-contract. This requires very careful checking as it can be difficult to identify every clause that is relevant and it results in a need to cross-reference between agreements; it also requires that sub-contractors have access to higher tier contracts.
- Drafting bespoke sub-contracts that reflect the rights and obligations in the main contract. While the end result is neater and simpler to understand than referencing, equal care needs to be taken in drafting.
- Using standard form contracts that already include back-to-back provisions in main contracts and sub-contracts.
Key aspects of construction contracts that might require back-to-back provisions include:
- Key dates, notification periods and other time-related procedures. For example, claims can fail if the timing of the sub-contract claims procedure does not give the main contractor sufficient time to make a claim themselves.
- Enforcement of dispute resolution findings and the right to participate in proceedings.
- A requirement that valid claims must be passed on.
- Allocation of liability for liquidated damages.
- Entitlement to extensions of time.
- Entitlement to loss and expense.
- Information and reporting requirements.
- The definition of completion.
- Obligations to achieve a certain quality and to comply with certain standards.
- Indemnities.
- Collateral warranties.
- Suspension and termination rights.
- Design responsibilities.
- Transfer of copyright.
The Housing Grants Construction and Regeneration Act prevents the inclusion of pay-when-paid or pay-when-certified clauses, and the release of retention (i.e retention monies) cannot be prevented by conditions within another contract.
[edit] Related articles on Designing Buildings
- Building Users' Insurance Against Latent Defects.
- Collateral warranties.
- Concession Contracts Regulations.
- Construction contracts.
- Contra charges.
- Flow-down term.
- Housing Grants Construction and Regeneration Act.
- Liberty Mercian Limited v Cuddy Civil Engineering Limited and others.
- Pay when paid.
- Proprietary information.
- Sub-consultants.
- Sub-contracts.
- Z clauses.
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.