Contract claims procedure
Contents |
[edit] Introduction
The process for making claims under a construction contract typically involves several key steps to ensure they are made in accordance with the contract terms and that they are properly documented and substantiated. This article presents an outline of common procedures, but ultimately the process required will depend on the exact wording of the contract and the application of relevant legislation such as the Housing Grants, Construction and Regeneration Act.
[edit] Identify the basis for the claim
Claims can arise from a number of situations, such as:
- Variations or changes to the work scope.
- Delays and disruptions.
- Unforeseen site conditions.
- Non-payment or late payment.
- Breach of contract terms.
For more information see: Contract claims.
[edit] Review the contract
Carefully review the construction contract to understand:
- The types of claims that can be made.
- The notice requirements.
- The time frames for submitting claims.
- The specific procedures for making a claim.
- The documentation required.
[edit] Notification
Most contracts require prompt notice of a claim. This notice should include:
[edit] Document the claim
This may include:
- Detailed records of the work performed.
- Correspondence (emails, letters).
- Site diaries and logs.
- Photographs and videos.
- Statements from witnesses.
- Schedules and programs.
[edit] Prepare the claim submission
Prepare a formal claim document, which typically includes:
- An introduction and summary of the claim.
- A detailed description of the events leading to the claim.
- The contractual basis for the claim (citing relevant contract clauses).
- Supporting documentation and evidence.
- Calculations of the claim value (e.g., costs incurred, delay impacts).
[edit] Submit the claim
Submit the claim to the other party (e.g., the employer, main contractor) in accordance with the contract’s procedures. Ensure that the submission is timely and includes all necessary documentation.
After submitting the claim, there may be a period of negotiation and discussion. The goal is to reach an agreement on the validity and value of the claim. This may involve:
- Meetings and discussions between the parties.
- Clarification and provision of additional information if requested.
- Adjustments to the claim based on feedback.
If the claim is not resolved through negotiation, the contract will typically provide for dispute resolution mechanisms, which may include mediation, adjudication (a statutory process under the Housing Grants, Construction and Regeneration Act 1996), arbitration or litigation.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Contract claims.
- Construction contract.
- Dispute avoidance.
- Dispute resolution.
- Disruption claims in construction.
- Evaluation of claims.
- Housing Grants, Construction and Regeneration Act.
- How to prepare a claim for an extension of time.
- Mediation.
- Scheme for Construction Contracts.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.