Breach of contract
If one of the parties to a contract fails to perform as required, this may constitute a breach of contract. A breach may entitle the innocent party to make a claim for damages for the losses it has suffered.
If the breach of contract is serious (a material breach), then the innocent party may also consider that it is discharged from any further obligations under the contract.
If the breach is less serious, (a non-material breach, sometimes referred to as a default) the innocent party may make a claim for damages, but may not consider it is discharged from any further obligations under the contract. This prevents the innocent party from excusing their own performance because of a minor breach of just one part of the contract.
This is generally the position on construction contracts, where some works are likely to have been carried out, but one or more may remain undone, incomplete or defective. As building contracts are usually divided up into parts (divisible), and include a series of separate payments, this sort of partial failure would not allow the innocent party to excuse their performance, i.e. a failure in one part will generally only mean that the innocent party is not liable to pay for that part. Furthermore, if the works have been substantially performed, then they must pay for them subject to a claim for the parts that have not been performed.
On construction contracts, it is generally in the interests of both parties for the contract to continue and for the works to proceed irrespective of minor problems. Whilst damages for breach of contract may seek to put the innocent party in the position it would have been in had there not been a breach of contract, the delay and disruption caused, for example, by having to appoint a new contractor can far outweigh the difficulties of proceeding, albeit under difficult circumstances.
Construction contracts generally make provisions for the contract to be varied without there being a breach. Variations, extensions of time, claims for loss and expense, liquidated damages, and the defects liability period all provide for the contract to be varied or for problems to be rectified.
Where one party behaves in such a way that it indicates it no longer intends to accept its obligations under the contract, this is considered to be a repudiatory breach (or fundamental breach), allowing the innocent party to terminate the contract and to sue for damages. Generally the contract will set out what those breaches are, but they might include:
- Refusal to carry out work.
- Abandoning the site.
- Removing plant from the site.
- Failure to make payments.
- Employing others to carry out the work.
- Failure to allow access to the site.
- Failure to proceed regularly and diligently.
- Failure to remove or rectify defective works.
Where repudiation is considered to have occurred, the innocent party can either affirm that the contract will continue or accept the repudiation and so terminate the contract. In either case, they will have the right to claim damages. Either way, it is important that there is some sort of response, as inaction may be considered to be an affirmation of the contract.
Assessing the seriousness of breaches of contract depends on the particular circumstances and terms of the contract. For example, if a contractor failed to carry out the work to an agreed timetable, this might be considered a relatively minor issue on some projects, whilst on others it could be an extremely serious breach. The innocent party must be careful therefore to establish that there has actually been a material breach before considering that the contract is terminated, otherwise they might find themselves in breach of contract.
This can lead to disputes, where for example, the client refuses to make payment, claiming that the contractor has failed to perform, whereas the contractor contends that they are not performing because the client has refused to make payment.
An anticipatory breach (or anticipatory repudiation) occurs when one of the parties to the contract declares to the other that they do not intend to perform their obligations under the contract.
The contract may also allow termination under other circumstances, such as frustration or insolvency. It may also allow termination for ‘convenience’, but this may leave the terminating party open to significant claims by the other party. See: Termination for more information.
Rescission is a process of returning both parties to the position they would have been in had they not entered into the contract. This might be appropriate for example if there is a serious error in the contract.
The term irremediable breach refers to a situation where there is a defect in the works for which the cost of rectification is unreasonable relative to the nature of the defect. Under these circumstances the contract administrator may issue a certificate of making good defects, with a deduction relative to the amount by with the value of the works has been reduced by the defect.
NB: The Construction Act now gives contractors the right to suspend performance for non-payment.
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution.
- Breach.
- Causes of construction disputes.
- Civil procedure rules.
- Concurrent delay.
- Construction Act.
- Contract claims.
- Defects.
- Dispute resolution boards.
- Extension of time.
- Fair payment practices.
- Frustration.
- Housing Forum seeks unity over suspension of works.
- Injunction.
- Legal action.
- Litigation.
- Liquidated damages.
- Liquidated v unliquidated damages.
- Loss and expense.
- Material breach.
- Non-material breach.
- Pre-action protocol for debt claims
- Remoteness.
- Repudiation.
- Subletting.
- Termination.
Featured articles and news
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese as well as English.