Defects in construction
Defects are aspects of the works that are not in accordance with the contract.
Defects may occur because of:
Defects can be 'patent' or 'latent'. Patent defects are those which can be discovered by reasonable inspection. Latent defects are those which cannot be discovered by reasonable inspection, for example problems with foundations which may not become apparent for several years after completion when settlement causes cracking in the building. When a latent defect becomes apparent, it becomes patent rather than latent.
During the defects liability period, the client reports any defects that arise to the contract administrator who decides whether they are defects in the works (i.e. works that are not in accordance with the contract), or whether they are in fact maintenance issues. If the contract administrator considers that they are defects, then they may issue instructions to the contractor to make good the defects within a reasonable time.
NB: It is the contractor's responsibility to identify and rectify defects, not the clients, so if the client does bring defects to the contractor's notice, they should make clear that this is not a comprehensive list of all defects.
At the end of the defects liability period, the contract administrator prepares a schedule of defects, listing those defects that have not yet been rectified, and agrees with the contractor the date by which they will be rectified. The contractor must in any event rectify defects within a reasonable time.
When the contract administrator considers that all items on the schedule of defects have been rectified, they issue a certificate of making good. This has the effect of releasing the remainder of any retention monies and will result in the issuing of the final certificate.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
This can put the contract administrator in a difficult position, where both the contractor and the client are keen to issue the certificate (so that the building can be handed over) and yet defects (more than a de minimis) are apparent in the works. Issuing the certificate under these circumstances could render the contract administrator liable for problems that this causes, for example, in the calculation of liquidated damages.
If the contract administrator is pressured to certify practical completion even though the works are not complete, they might consider informing the client in writing of the potential problems of doing so, obtaining written consent from the client to certify practical completion and obtaining agreement from the contractor that they will complete the works and rectify any defects. If the contract administrator is not confident about the potential problems that may result from early certification, they might advise the client to seek legal advice.
After the defects liability period, the building owner does not have a contractual right to insist that the contractor rectifies defects not notified during that period. The building owner must instead seek redress in an action for damages, for breach of contract, or for negligence. In the case of dwellings there is a statutory remedy provided by the Defective Premises Act 1972. These rights of action are not perpetual; actions for breach of contract are time barred after six years from the date of the breach (usually the completion of the building although with a failure of design the breach may have occurred earlier), or for a contract under seal, the period is 12 years
For more information see: Latent defects.
NB: NEC suggests that in the ECC (Engineering and Construction Contract), a defect is '...a part of the works which is not as stated in the Works Information or not in accordance with applicable law or the accepted design. There is a reciprocal obligation on both the supervisor and contractor to notify each other as soon as they are aware of a Defect.' At or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no defects, or lists any uncorrected defects.
In a submission to the Inquiry into the Construction of Edinburgh Schools in 2016, the Royal Incorporation of Architects in Scotland (RIAS) criticised the transfer of responsibility from construction professionals to other parties less involved with the design process and sited the dilution of the role of the design team as one of the causes of poor quality construction. See Inquiry into the construction of Edinburgh schools view of the RIAS for more information.
[edit] Related articles on Designing Buildings Wiki
- Aftercare manager.
- Alkali-silica reaction (ASR).
- Building pathology.
- Certificate of making good defects.
- Common mistakes on building drawings.
- Corrosion.
- Cracking and building movement.
- Creep.
- Decennial liability.
- Defective Concrete Blocks Grant Scheme.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects in brickwork.
- Defects in dot and dab.
- Defects in stonework.
- Defects liability period.
- Defects list.
- Degradation of construction materials.
- Design liability.
- Deterioration.
- Dilapidations.
- Failure modes and effect analysis (FMEA).
- Failure of metals.
- Fit for purpose.
- Flat roof defects.
- Flooring defects.
- Forensic investigations: can we trust them?
- Guarantees.
- Housing defects.
- Latent defects.
- Making good.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Professional consultant's certificate.
- Professional indemnity insurance.
- Punch list.
- Pyrite and mica redress issues in Dail Eireann.
- Reasonable skill and care.
- Remedial work.
- Retention bond.
- Roofing defects.
- Schedule of defects.
- Surfside condo collapse: climate change demands adaptation in design and approach.
- Using satellite imagery to monitor movements in megaprojects.
- Why do buildings crack? (DG 361).
- Workmanship.
[edit] External references
- Blake-Turner & Co. Solicitors: Building defects; the legal position.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.