Defects date
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration. The third edition, NEC3 was published in 2005.
According to NEC, a defect is ‘…a part of the works which is not as stated in the Works Information or not in accordance with applicable law or the accepted design.’
Until the defects date, there is an obligation on both the supervisor and contractor to notify each other as soon as they are aware of a defect, although the contractor is obliged to rectify a defect whether or not they have been notified of it, and may even be instructed to search for a defect, although the reason for this must be given in the instruction.
The defects date is set out in the contract data and is a duration from the completion date, rather than a specific day. That is, the duration is the same whether or not the completion date set out in the contract is achieved. Typically the defects date is 26 or 52 weeks from the completion date.
The defects date is the last date on which the supervisor or the contractor can give a notification of defects and is also the last date on which compensation events can be notified.
At, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no remaining patent defects, or lists any uncorrected defects. This triggers the release of any remaining retention, although if there are any remaining defects listed on the defects certificate, a withholding notice may be served and retention may continue to be held.
The defect correction period defines the maximum period within which the contractor must rectify a notified defect. Different defect correction periods can be specified for different types of defects. The only circumstances when the defects certificate might not be issued on the defects date is if a previously notified defect has a defects correction period that ends after the defects date, in which case it is issued on the later date.
If notified defects are not rectified within the defect correction period, they may be rectified by others and the cost reimbursed by the contractor.
The parties to the contract are permitted to agree that certain defects need not be rectified, and in this case the contractor must submit a quotation for reduced prices, an earlier completion date or both, and an adjustment is then made to the works information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Certificate of making good defects.
- Decennial liability.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Defects liability period.
- Defects.
- Defects certificate.
- Defects correction period.
- Delay damages.
- Dilapidations.
- Fit for purpose.
- Guarantees.
- Inspection.
- Latent defects.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Reasonable skill and care.
- Remedial work.
- Schedule of condition.
- Schedule of defects.
- Scott schedule.
- Site inspection.
- Site inspector.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.