New Engineering Contract
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
The intentions of NEC contracts include:
- Stimulating good management.
- Being clear and simple, written in plain English, in the present tense and without legal terminology.
- Being useable in wide variety of situations from minor works to major projects
The suite of documents now include:
- NEC4: Alliance Contract
- NEC4: Design Build and Operate Contract
- NEC4: Dispute Resolution Service Contract
- NEC4: Engineering and Construction Contract
- NEC4: Engineering and Construction Short Contract
- NEC4: Engineering and Construction Short Subcontract
- NEC4: Facilities Management Contract
- NEC4: Facilities Management Short Contract
- NEC4: Facilities Management Short Subcontract
- NEC4: Facilities Management Subcontract
- NEC4: Framework Contract
- NEC4: Professional Service Contract
- NEC4: Professional Service Short Contract
- NEC4: Professional Service Subcontract
- NEC4: Supply Contract
- NEC4: Supply Short Contract
- NEC4: Term Service Contract
- NEC4: Term Service Short Contract
- NEC4: Term Service Subcontract
The Engineering and Construction Contract has 6 options:
- NEC4: Engineering and Construction Contract Option A priced contract with activity schedule
- NEC4: Engineering and Construction Contract Option B: priced contract with bill of quantities
- NEC4: Engineering and Construction Contract Option C: target contract with activity schedule
- NEC4: Engineering and Construction Contract Option D: target contract with bill of quantities
- NEC4: Engineering and Construction Contract Option E: cost reimbursable contract
- NEC4: Engineering and Construction Contract Option F: management contract
There are a number of articles relating to NEC on Designing Buildings:
- Accepted programme.
- Activity schedule
- Compensation event.
- Cost reimbursable contract.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early contractor involvement.
- Early warning notice.
- Key dates.
- Latham Report.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC contracts and collaborative working.
- NEC early contractor involvement.
- NEC early warning notices - a tool of mutual benefit.
- NEC3.
- NEC4.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- Period for reply.
- Term Contract.
- The NEC and the Z clause.
- Time Risk Allowance.
- Z clauses.
[edit] Related articles on Designing Buildings
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.