Disallowed cost
|
Under cost reimbursable contracts, the contractor is paid actual costs – a calculation based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis – some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the New Engineering Contract (NEC) and Engineering and Construction Contract contract (EEC), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’. The disallowed cost does not have to be paid by the employer and so is borne by the contractor. As a result, this is a common area of dispute.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment and people), minus the disallowed cost.
The disallowed cost may include costs that appear to fall within the definition of defined cost, but that have been incurred as a result of the contractor’s failure or default.
This includes:
- Amounts that should not have been paid to a subcontractor.
- Amounts that are not justified by the contractor’s records.
- Resources that were not used.
- Costs incurred because the contractor did not follow the proper procedure.
- Failure to give early warning of anything that may delay the works, or increase costs.
- Defects corrected after completion.
- Preparation for adjudication.
Some defects corrected before completion are not disallowed. However, if a target cost (pain/gain) contract is being used, this will increase the defined cost, and so the potential ‘gain’ for the contractor is reduced, and the likelihood of ‘pain’ is increased. As a result, the contractor may in fact still end up paying for some of the costs of the defect.
The project manager decides whether a cost is disallowed. This must be done in accordance with the contract, and a reason must be given for each disallowed cost through the certification process.
[edit] Related articles on Designing Buildings Wiki:
- Atkins v Secretary of State for Transport.
- Alternative Dispute Resolution legislation.
- Compensation event.
- Contract conditions.
- Cost reimbursable contract.
- Defect.
- Defined cost.
- Delay damages.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Outturn cost.
- Period for reply.
- Target cost.
- Time Risk Allowance TRA.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.

























