Cost reimbursable contract
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee. Option E of the NEC3 Engineering and Construction Contract (ECC) is an example of a cost reimbursable contract.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business). Tendering may proceed based on an outline specification, any drawings and an estimate of costs.
This is a high risk form of contracting for the client as the final cost is not known when the contract is entered into (i.e. there is no contract sum).
The costs for which the contractor is entitled to be reimbursed must be set out very clearly in the contract. This is a complex procedure that needs to be carefully considered, as whilst some direct costs may be relatively straight forward to determine, whilst other ‘shared’ costs, might not.
Direct costs that are clearly attributable to a single project could include:
- Labour.
- Materials.
- Hired plant.
- Sub-contractors.
Other costs that might be spread across more than one project could include:
- Head office costs.
- Staff costs.
- Manufacturing facilities.
- Owned plant.
These costs might be calculated on a pro-rata basis and charged, along with profits as a pre-agreed lump sum, or percentage fee.
In order that the contractor can maintain their cash flow, cost reimbursable contracts may also allow them to charge for liabilities, or for costs that will be incurred before the next interim payment.
Costs are calculated based on the contractor’s accounts and other records, which are made available to the client on an ‘open book’ basis. The client may also monitor activities on site to verify that costs are legitimate (for example, checking whether plant that is being charged is actually being used) and that costs are not excessive. This can become complex where the contractor is thought to be operating inefficiently or incompetently.
The contractor can be incentivised to operate efficiently by the introduction of a target cost. Here, a target cost is agreed at the beginning of the project. At the end of the project the actual cost is compared to the target cost (taking into account any changes that have been agreed). If the actual cost is lower than the target cost, the savings are shared between the parties to the contract on some pre-agreed basis (often a percentage). If the actual cost is higher than the target cost, the additional costs may also be shared.
NB: JCT suggest that a prime cost contract, cost plus and cost reimbursable contract are in fact the same thing. Others consider that a prime cost contract is one in which the cost of works packages (the prime cost) are reimbursed, but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
There are three types of cost reimbursable methods used in the construction industry.
- Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
- Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
- Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Related articles on Designing Buildings
- Admeasurement.
- Contractor.
- Construction contract.
- Contract conditions.
- Contract sum.
- Defined cost.
- Disallowed cost.
- Interim certificate.
- Key dates.
- NEC Option E: Cost reimbursable contract.
- NEC3.
- Open-book accounting.
- Prime cost contract.
- Procurement route.
- Remeasurement.
- Specification.
- Sub-contractors.
- Target cost.
- Tender.
- Time and material contract (T&M).
[edit] External references
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.