Prime cost contract
Prime cost contracts (such as JCT PPC 11) are sometimes called cost plus contracts or cost reimbursement contracts.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete.
This method of procurement is not generally recommended, but it can be useful under particular circumstances where an immediate start on site is necessary (for example for urgent alteration or repair work, or if there has been a building failure or a fire, requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Tendering proceeds based on an outline specification, any drawings and an estimate of costs. The contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. The fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
Other basis for payment are possible, including combinations of lump sum and percentage fees. For example, it might be possible to fix some elements of overheads whilst applying a percentage to other elements and to profit.
This is a high risk form of procurement for the client as they are reliant on the contractor working efficiently and procuring sub-contracts economically. Sub contracts may be procured competitively, but there may be little incentive for the contractor to secure or select economic bids. Some of these difficulties can be mitigated if a partnering relationship has been established between the client and the contractor.
NB: Some people consider that a cost reimbursable contract or cost plus contract is one in which the client takes all the risk, whereas a prime cost contract is one in which the cost of the works packages (the prime cost) are reimbursed but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
[edit] Related articles
Featured articles and news
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
For small alternation project of 8 storey building, what is the advantage of using prime cost contract?
Unless an immediate start is needed - for example if there is some danger or urgency, it is difficult to see what the advantage would be over a traditional contract.