JCT Design and Build Contract
The Joint Contracts Tribunal (JCT) Design and Build Contract (DB) is intended for use on construction projects following the design and build procurement route. This involves appointing a main contractor to design (or complete the design) of the project and then to go on and construct it. This is as opposed to the traditional procurement route in which the client appoints consultants to design the project and then a contractor is appointed to construct it.
Design and build gives a single point of responsibility for delivering the entire project, and can help ensure good buildability, cost control and speed. Some clients however, consider it is only appropriate for simple projects, where retaining control over the design is not the main priority.
The scale and complexity of design and build projects can vary considerably, but the DB contract is generally suitable for projects where a detailed agreement is required, making provision for collaborative working, sustainability, advance payment, third party rights, bonds, collateral warranties and so on.
The 2016 edition of the contract includes the following documents:
- Design and Build contract guide (DB/G).
- Design and Build sub-contract agreement (DBSub/A).
- Design and Build sub-contract conditions (DBSub/C).
- Short form of sub-contract (ShortSub): For small-scale subcontract works that are simple and involve low risk.
- Sub-subcontract (SubSub).
- Design and Build sub-contract guide (DBSub/G).
- Design and Build contract (DB) Tracked Change Document: Highlights the changes between the DB 2011 and 2016 editions.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Construction management contract.
- Design and build.
- Design and build - pros and cons.
- Intermediate building contract.
- JCT.
- JCT minor works building contract.
- JCT Sub-subcontract.
- Major project construction contract.
- Management Building Contract.
- Prime cost contract.
- Standard Building Contract.
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
Comments
If the design build contractor is the actual designer and is responsible to procure the materials but not required to build. Can he change the material prices after signing the contract
What does the contract say - does it allow them to change prices? eg are fluctuations allowed?