JCT Design and Build Contract
The Joint Contracts Tribunal (JCT) Design and Build Contract (DB) is intended for use on construction projects following the design and build procurement route. This involves appointing a main contractor to design (or complete the design) of the project and then to go on and construct it. This is as opposed to the traditional procurement route in which the client appoints consultants to design the project and then a contractor is appointed to construct it.
Design and build gives a single point of responsibility for delivering the entire project, and can help ensure good buildability, cost control and speed. Some clients however, consider it is only appropriate for simple projects, where retaining control over the design is not the main priority.
The scale and complexity of design and build projects can vary considerably, but the DB contract is generally suitable for projects where a detailed agreement is required, making provision for collaborative working, sustainability, advance payment, third party rights, bonds, collateral warranties and so on.
The 2016 edition of the contract includes the following documents:
- Design and Build contract guide (DB/G).
- Design and Build sub-contract agreement (DBSub/A).
- Design and Build sub-contract conditions (DBSub/C).
- Short form of sub-contract (ShortSub): For small-scale subcontract works that are simple and involve low risk.
- Sub-subcontract (SubSub).
- Design and Build sub-contract guide (DBSub/G).
- Design and Build contract (DB) Tracked Change Document: Highlights the changes between the DB 2011 and 2016 editions.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Construction management contract.
- Design and build.
- Design and build - pros and cons.
- Intermediate building contract.
- JCT.
- JCT minor works building contract.
- JCT Sub-subcontract.
- Major project construction contract.
- Management Building Contract.
- Prime cost contract.
- Standard Building Contract.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
If the design build contractor is the actual designer and is responsible to procure the materials but not required to build. Can he change the material prices after signing the contract
What does the contract say - does it allow them to change prices? eg are fluctuations allowed?