JCT Major project construction contract
The term ‘major project’ typically refers to; ‘A bespoke project, programme or portfolio characterised by its complexity, level of investment and stakeholder involvement. Such a project is likely to have its own project control office established and have a dedicated project team under the direct control of a nominated person.' (Ref GRIP Manual, Introduction to the Project Management manual, published by Network Rail in 2006).
Major project construction contracts (such as JCT MP 2016), are intended for use by employers who are involved in procuring large-scale construction projects.
JCT MP 2016 is a design and build contract, under which responsibility for the design, as well as completing the construction works, lies with the contractor.
The design can be produced by the contractor from the outset, using specialist designers or an in-house team; or it can be produced based on a concept provided by the employer’s advisers. If the initial concept is prepared by the employer's advisers, they may then be novated to work for the contractor to develop the detailed design and inspect the construction works as they proceed.
The employer will have prepared employer's requirements on which the contractor can base their design, and the employer will usually appoint an employer's representative to exercise their powers and functions.
The contract is suitable for use on framework agreements, and for both the public and private sector. It may also be used with a Pre-Construction Services Agreement (General Contractor) (PCSA) or Pre-Construction Services Agreement (Specialist) (PCSA/SP).
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.