Cost reimbursable contract
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee. Option E of the NEC3 Engineering and Construction Contract (ECC) is an example of a cost reimbursable contract.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business). Tendering may proceed based on an outline specification, any drawings and an estimate of costs.
This is a high risk form of contracting for the client as the final cost is not known when the contract is entered into (i.e. there is no contract sum).
The costs for which the contractor is entitled to be reimbursed must be set out very clearly in the contract. This is a complex procedure that needs to be carefully considered, as whilst some direct costs may be relatively straight forward to determine, whilst other ‘shared’ costs, might not.
Direct costs that are clearly attributable to a single project could include:
- Labour.
- Materials.
- Hired plant.
- Sub-contractors.
Other costs that might be spread across more than one project could include:
- Head office costs.
- Staff costs.
- Manufacturing facilities.
- Owned plant.
These costs might be calculated on a pro-rata basis and charged, along with profits as a pre-agreed lump sum, or percentage fee.
In order that the contractor can maintain their cash flow, cost reimbursable contracts may also allow them to charge for liabilities, or for costs that will be incurred before the next interim payment.
Costs are calculated based on the contractor’s accounts and other records, which are made available to the client on an ‘open book’ basis. The client may also monitor activities on site to verify that costs are legitimate (for example, checking whether plant that is being charged is actually being used) and that costs are not excessive. This can become complex where the contractor is thought to be operating inefficiently or incompetently.
The contractor can be incentivised to operate efficiently by the introduction of a target cost. Here, a target cost is agreed at the beginning of the project. At the end of the project the actual cost is compared to the target cost (taking into account any changes that have been agreed). If the actual cost is lower than the target cost, the savings are shared between the parties to the contract on some pre-agreed basis (often a percentage). If the actual cost is higher than the target cost, the additional costs may also be shared.
NB: JCT suggest that a prime cost contract, cost plus and cost reimbursable contract are in fact the same thing. Others consider that a prime cost contract is one in which the cost of works packages (the prime cost) are reimbursed, but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
There are three types of cost reimbursable methods used in the construction industry.
- Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
- Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
- Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Related articles on Designing Buildings
- Admeasurement.
- Contractor.
- Construction contract.
- Contract conditions.
- Contract sum.
- Defined cost.
- Disallowed cost.
- Interim certificate.
- Key dates.
- NEC Option E: Cost reimbursable contract.
- NEC3.
- Open-book accounting.
- Prime cost contract.
- Procurement route.
- Remeasurement.
- Specification.
- Sub-contractors.
- Target cost.
- Tender.
- Time and material contract (T&M).
[edit] External references
Featured articles and news
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Key points and relevance to construction of meeting, due to reconvene.