Interim certificates in construction contracts
Contents |
[edit] What are interim certificates?
Interim certificates provide a mechanism for the client to make payments to the contractor during the construction process, before the works are complete. The Housing Grants, Construction and Regeneration Act, states that a party to a construction contract in excess of 45 days is entitled to interim or stage payments.
[edit] How are interim payments made?
Interim payments can be agreed in advance and paid at particular milestones, but they are more commonly, regular payments, the value of which is based on the value of work that has been completed (this is the actual value of the work completed, taking into account variations, etc.).
The amount of these payments is entered onto an interim certificate (generally valued by the cost consultant, perhaps having taken advice from the lead designer) and the client must honour the certificate within the period stipulated by the contract.
If the client intends to pay a different amount from that shown on the interim certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice)
For more information see: Housing Grants, Construction and Regeneration Act.
[edit] How are interim payments valued?
The value of interim certificates is the value of the work completed, less any amounts already paid, less retention. Half of this retention will be released on certification of practical completion and the other half upon issue of the certificate of making good defects.
Interim certificates should make clear the amount of retention and a statement should also be prepared showing retention for nominated sub-contractors if there are any. The contract may require that retention is kept in a separate bank account and that this is certified. In this case, the client will generally keep any interest paid on the account.
For more information see: Retention.
There may be provision to include the value of particularly costly materials that the contractor has not yet delivered to site. This allows the contractor to order items in good time, without incurring unnecessary long-term expense, but does put the client at some risk if the contractor becomes insolvent.
For more information see: Off-site goods and materials.
On design and build projects, the amounts certified as payable may be based on the contract sum analysis.
The contract conditions provide that the contract administrator must issue an interim certificate within five calendar days of the due date whether or not the contractor has issued an interim payment application. This five calendar day period is set by statute in the Housing Grants, Construction Regeneration Act 1996 as amended by the Local Democracy, Economic Development and Construction Act 2009.
For more information see: Payment notice.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Certificate of making good defects.
- Certificates in the construction industry.
- Contract sum analysis.
- Cost value reconciliation.
- Drawdown.
- Due date.
- Final certificate.
- Housing Grants, Construction and Regeneration Act.
- Interim valuation.
- Off site materials.
- Milestone payment.
- Payment notice.
- Payments to nominated sub-contractors.
- Practical completion.
- Retention.
[edit] External references
- RICS Valuations for interim certificates.
- Allan K Construction contracts 2017 @qs 2 kings entertainment
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Interim Payment Certificate is prepared by Consultant's Team Leader or Contractor's Project Manager's which reports Monthly progress schedule and progress cash-flow.