Payments to nominated sub-contractors
A nominated sub-contractor is one that is selected by the client to carry out an element of the works and then imposed on the main contractor after the main contractor has been appointed. This allows the client to have direct, separate negotiations with major suppliers of goods or services and feed their appointment and design input into the contract after works by the main contractor have commenced.
There is no direct contractual relationship between the client and the nominated sub-contractor.
The main contractor is instructed by the client to use a nominated sub-contractor for a particular element of the works through the inclusion of a prime cost sum (based on the nominated sub-contractor’s accepted quotation) to which the main contractor is entitled to add mark up and attendance costs (such as material handling, use of site facilities, scaffolding, and so on).
The main contractor should specify the general preliminaries available to the nominated sub-contractor, and specific items of preliminaries to be provided by the sub-contractor.
Before any order is placed the main contractor should be consulted as to whether the sub-contractor's proposals are acceptable, including matters relating to preliminaries.
When the nominated sub-contractor works are being carried out, the client’s cost consultant will periodically value their work and the amount properly due is then shown as a separate amount on interim certificates. This amount is also notified to the nominated sub-contractor.
The contractor must then pay the nominated sub-contractor the certified amount. The contract may allow the client to pay the nominated sub-contractor directly if the main contractor fails to do so.
As the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for failure of the nominated sub-contractor to perform. However, as the contract for the nominated sub-contractor is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated sub-contractor to guarantee performance and to indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
[edit] Related articles on Designing Buildings Wiki
- Construction supply chain payment charter.
- Domestic sub-contractor.
- Fair payment practices.
- Interim certificates.
- Main contractor’s discount.
- Named sub-contractor.
- Nominated sub-contractor.
- Nominated subcontractor v named subcontractor.
- Nominated supplier.
- Payment period.
- Prime cost sum.
- Procurement route.
- Remedies for late payment.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.