Nominated subcontractor v named subcontractor
Contents |
[edit] Introduction
Contractors may not have all the required skills or resources necessary to complete the works described in a construction contract, and so sub-contractors are commonly appointed to undertake those aspects of the project.
Typically, subcontractors are selected and appointed by the contractor themselves. These are referred to as ‘domestic’ subcontractors.
For more information see: Subcontractors.
[edit] Nominated subcontractors
Under certain circumstances, the client may wish to select (nominate) a subcontractor themselves, rather than allowing the contractor to select them. This is referred to as a nominated subcontractor.
This can happen; where the client has involved a subcontractor in the design process, where the client wishes to achieve a very specific outcome, where they have an existing relationship, or where the client needs to secure the supply of long lead-time items. Nominated subcontractors may be selected before or after the contract is entered into with the main contractor.
Ultimately, the nominated subcontractor is still appointed by the main contractor, but they are imposed on them by the client. This can be allowed for in the contract by a prime cost sum, to which the contractor is permitted to add profit and attendance.
Nominated subcontractors are less common in the UK than they used to be, and some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for the nomination of sub-contractors. This is because the contractual arrangements allowing nomination are very complicated, and as the main contractor has no choice in the selection of the nominated sub-contractor, the contract may, or may not hold them entirely responsible for failure of the nominated sub-contractor to perform (depending on the exact wording of the contract). The contractor will however generally be allowed the right to object to the subcontractor under certain conditions, and if the client still wishes to use the subcontractor, some contracts allow them to indemnify the main contractor against the possible consequences of this.
Because of these and other complexities, nomination is generally not used in UK contracts (such as JCT contracts), where the use of named sub-contractors is now generally considered to be a simpler alternative. However, some contracts still allow nomination, particularly international contracts such as FIDIC.
For more information see: Nominated subcontractor.
[edit] Named subcontractors
Naming subcontractors allows the client to influence the selection of sub-contractors whilst leaving responsibility for their performance with the main contractor.
The client names a short-list of subcontractors that would be acceptable to them in the tender documents for the main construction contract. The tender documents allow for this by including a provisional sum for the subcontract package. When tendering for the main contract, the main contractor makes allowances for mark up, attendance and programme in relation to the subcontract package.
Once appointed, the main contractor seeks tenders for the package from the named sub-contractors (although they may reasonably object to any of the named subcontractors). Once the main contractor has selected and appointed a subcontractor the provisional sum is replaced with the actual price agreed.
The main contractors assumes responsibility for the subcontractor’s performance. In effect the named sub-contractor becomes a domestic subcontractor, they are paid by the main contractor and the main contractor is responsible for their works.
For more information see: Named subcontractor.
[edit] Related articles on Designing Buildings
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
I thought nominated sub-contractor provision under JCT was removed in 2005 - Now we have listed (clause 3.8 in SBC) and named specialist (supplemental provision)