Nominated subcontractor v named subcontractor
Contents |
[edit] Introduction
Contractors may not have all the required skills or resources necessary to complete the works described in a construction contract, and so sub-contractors are commonly appointed to undertake those aspects of the project.
Typically, subcontractors are selected and appointed by the contractor themselves. These are referred to as ‘domestic’ subcontractors.
For more information see: Subcontractors.
[edit] Nominated subcontractors
Under certain circumstances, the client may wish to select (nominate) a subcontractor themselves, rather than allowing the contractor to select them. This is referred to as a nominated subcontractor.
This can happen; where the client has involved a subcontractor in the design process, where the client wishes to achieve a very specific outcome, where they have an existing relationship, or where the client needs to secure the supply of long lead-time items. Nominated subcontractors may be selected before or after the contract is entered into with the main contractor.
Ultimately, the nominated subcontractor is still appointed by the main contractor, but they are imposed on them by the client. This can be allowed for in the contract by a prime cost sum, to which the contractor is permitted to add profit and attendance.
Nominated subcontractors are less common in the UK than they used to be, and some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for the nomination of sub-contractors. This is because the contractual arrangements allowing nomination are very complicated, and as the main contractor has no choice in the selection of the nominated sub-contractor, the contract may, or may not hold them entirely responsible for failure of the nominated sub-contractor to perform (depending on the exact wording of the contract). The contractor will however generally be allowed the right to object to the subcontractor under certain conditions, and if the client still wishes to use the subcontractor, some contracts allow them to indemnify the main contractor against the possible consequences of this.
Because of these and other complexities, nomination is generally not used in UK contracts (such as JCT contracts), where the use of named sub-contractors is now generally considered to be a simpler alternative. However, some contracts still allow nomination, particularly international contracts such as FIDIC.
For more information see: Nominated subcontractor.
[edit] Named subcontractors
Naming subcontractors allows the client to influence the selection of sub-contractors whilst leaving responsibility for their performance with the main contractor.
The client names a short-list of subcontractors that would be acceptable to them in the tender documents for the main construction contract. The tender documents allow for this by including a provisional sum for the subcontract package. When tendering for the main contract, the main contractor makes allowances for mark up, attendance and programme in relation to the subcontract package.
Once appointed, the main contractor seeks tenders for the package from the named sub-contractors (although they may reasonably object to any of the named subcontractors). Once the main contractor has selected and appointed a subcontractor the provisional sum is replaced with the actual price agreed.
The main contractors assumes responsibility for the subcontractor’s performance. In effect the named sub-contractor becomes a domestic subcontractor, they are paid by the main contractor and the main contractor is responsible for their works.
For more information see: Named subcontractor.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
I thought nominated sub-contractor provision under JCT was removed in 2005 - Now we have listed (clause 3.8 in SBC) and named specialist (supplemental provision)