Named specialist work in construction
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars.
This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
This is similar to provisions for named subcontractors in some other forms of contract, and its inclusion is seen to be a result of the omission of provisions for nominated subcontractors from the JCT Standard Building Contract since 2005.
If the naming of specialists is required, a series of standard clauses and amendments must be incorporated into the contract. There are two ways in which the specialist provisions can work:
- Pre-named specialist work: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist work: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
This may entitle to contractor to an extension of time and /or loss and expense.
The contractor should enter into a contract with the specialist as soon as ‘reasonably practicable’ using a JCT Standard Building Sub-Contract.
The contract administrator must be notified if a contract cannot be entered by the contractor as required. On receipt of this notification the contract administrator must provide instruction to the contractor to either:
- Remove or solve whatever is preventing the contract.
- Select an alternative specialist.
- Undertake the work itself.
- Omit the work altogether.
If the contractor wishes to terminate the specialist’s employment, they must notify the contract administrator and, if required, the employer. The contractor can only give notice of termination or of repudiation after 14 days, unless the specialist has become insolvent.
If the contractor terminates the specialist’s employment, the contract administrator must issue instructions to the contractor to either:
- Name an alternative specialist.
- Undertake the work itself or through its sub-contractor.
- Omit the work altogether.
If the named specialist becomes insolvent the contractor may be entitled to an extension of time and /or loss and expense.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Extension of time.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Loss and expense.
- Named subcontractor.
- Nominated subcontractor.
- Nominated subcontractor v named subcontractor.
- Operative.
- Reasonable objection to a named specialist.
- Repudiation.
- Selected subcontractor.
- Specialist subcontractor.
- Sub-contract.
- Subcontractor.
- Supplier.
[edit] External references
- ‘The JCT Standard Building Contract 2011’, CHAPPELL, D., John Wiley and Sons (2015)
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.