Articles of agreement
![]() |
Contents |
[edit] Introduction
Contract documents for a construction contract will typically consist of:
- Contract drawings.
- Priced bill of quantities.
- Articles of agreement.
- Contract conditions.
- For contracts where there is a contractor’s designed portion: employer’s requirements, contractor’s proposals and contract sum analysis.
The ‘articles of agreement’ set out the core obligations of the parties involved. Typically, they consist of four sections:
- Recitals.
- Articles.
- Contract Particulars.
- Attestation.
By way of an example, the contents of the articles of agreement in the JCT Standard Building Contract (SBC) are set out below in more detail.
[edit] Recitals
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. Seven recitals describe what is required and the events that have taken place.
[edit] First recital
Describes the work required by the employer, identifies the site, confirms the preparation of the design and bill of quantities.
[edit] Second recital
Confirms that a priced copy of the bill of quantities has been supplied by the contractor to the employer, with a priced activity schedule where required.
[edit] Third recital
Identifies the contract drawings.
[edit] Fourth recital
Identifies whether the employer is to be considered a contractor for tax deduction purposes under the Construction Industry Scheme.
[edit] Fifth recital
Refers to an information release schedule provided to the contractor by the employer (this is optional).
[edit] Sixth recital
Clarifies whether the works are to be carried out in sections.
[edit] Seventh recital
This only applies (along with three more recitals), where the contractor is obliged to complete design works under the provisions for a contractor’s designed portion.
[edit] Articles
These set out what is agreed between the parties.
[edit] Article 1
The obligation of the contractor, i.e. undertaking and completing the works subject to the contract documents.
[edit] Article 2
The obligation of the employer, i.e. to pay the contract sum or such other sum as becomes payable under the contract (through variations and/or correction of errors).
[edit] Article 3
Identifies the architect (or contract administrator) under the contract, and provides the employer with the power to maintain someone in the role of duty-holder (or employer’s agent).
[edit] Article 4
Identifies the quantity surveyor.
[edit] Article 5
Identifies the principal designer.
[edit] Article 6
Identifies the principal contractor.
[edit] Article 7
Makes reference to the right to adjudication in the event of any dispute.
[edit] Article 8
Makes reference to the right to arbitration in the event of any dispute.
[edit] Contract particulars
This section sets out the aspects of the contract that are particular to the project to which the contract relates. It is a schedule for the variables in the agreement and conditions. It is important that the variables are compatible with the relevant operating mechanism in the agreement, conditions and schedules as disputes may arise when either party applies the contract particulars information without proper reference to the operating clause.
Read more about contract particulars here.
[edit] Attestation
The attestation is the process of confirming that something is correct or genuine, or that a particular requirement has been met. It may be completed:
[edit] Under seal
Signed by both parties, witnessed and made clear that it is executed as a deed.
[edit] Under hand
A ‘simple contract’ that is signed just by the parties.
[edit] Related articles on Designing Buildings Wiki
- Agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Contract execution.
- Contract negotiation.
- Contracts under seal v under hand.
- Essentials of a contract.
- FIDIC.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Named specialist work.
- NEC3.
- Period for reply.
- Procurement route.
- Sub-contract.
- Z clauses.
[edit] External references
- ‘The JCT 05 Standard Building Contract’ (2nd ed.), NDEKUGRI, I., RYCROFT, M., Butterworth-Heinemann (2009)
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Preparing for the future: how specifiers can lead the way
Effective specificationand the Future Homes Standard.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February