Reasonable objection to a named specialist
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars. This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
There are two ways in which the specialist provisions operate:
- Pre-named specialist: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
The grounds for reasonable objection by the contractor could include:
- The specialist has a poor safety record.
- If there are reasonable grounds for believing that the specialist may not be financially secure, solvent, reliable or technically competent.
- If the tender sum is not believed to be financially viable.
- Where the programme is deemed to be unreasonable.
Similar provisions are permitted where the contractor is unable to enter into a contract with the named specialist, or where the contractor terminates the specialist’s employment.
If the contractor proposes their own specialist, the employer has seven days from the point at which the contractor notifies them of the proposed replacement to raise any reasonable objection themselves.
The employer may object to the proposed specialist on the grounds that there will be a sub-standard performance. However, since the contractor remains responsible for the performance under the contract, it is rare that such an objection would be deemed valid. Where the employer has a realistic concern that liquidated damages for any delay that arises due to sub-standard performance is an inadequate remedy, the objection may be judged to be reasonable. Likewise if the employer has concerns about the contractor having the resources to fulfil their obligations in the event of things going wrong.
In the event of an objection raised by the employer being deemed reasonable, the contractor must propose a further replacement for consideration.
Adjudication can be used if necessary to determine what constitutes a reasonable objection.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Construction contracts.
- Contract conditions.
- Extension of time.
- Joint Contracts Tribunal.
- Named specialist work.
- Named subcontractor.
- Nominated subcontractor.
- Subcontractor.
- Supplier.
External references
- ‘The JCT Major Project Form’, JONES, N. F., Blackwell Publishing, (2004)
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.