Named specialist work in construction
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars.
This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
This is similar to provisions for named subcontractors in some other forms of contract, and its inclusion is seen to be a result of the omission of provisions for nominated subcontractors from the JCT Standard Building Contract since 2005.
If the naming of specialists is required, a series of standard clauses and amendments must be incorporated into the contract. There are two ways in which the specialist provisions can work:
- Pre-named specialist work: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist work: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
This may entitle to contractor to an extension of time and /or loss and expense.
The contractor should enter into a contract with the specialist as soon as ‘reasonably practicable’ using a JCT Standard Building Sub-Contract.
The contract administrator must be notified if a contract cannot be entered by the contractor as required. On receipt of this notification the contract administrator must provide instruction to the contractor to either:
- Remove or solve whatever is preventing the contract.
- Select an alternative specialist.
- Undertake the work itself.
- Omit the work altogether.
If the contractor wishes to terminate the specialist’s employment, they must notify the contract administrator and, if required, the employer. The contractor can only give notice of termination or of repudiation after 14 days, unless the specialist has become insolvent.
If the contractor terminates the specialist’s employment, the contract administrator must issue instructions to the contractor to either:
- Name an alternative specialist.
- Undertake the work itself or through its sub-contractor.
- Omit the work altogether.
If the named specialist becomes insolvent the contractor may be entitled to an extension of time and /or loss and expense.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Extension of time.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Loss and expense.
- Named subcontractor.
- Nominated subcontractor.
- Nominated subcontractor v named subcontractor.
- Operative.
- Reasonable objection to a named specialist.
- Repudiation.
- Selected subcontractor.
- Specialist subcontractor.
- Sub-contract.
- Subcontractor.
- Supplier.
[edit] External references
- ‘The JCT Standard Building Contract 2011’, CHAPPELL, D., John Wiley and Sons (2015)
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.