Reasonable objection
[edit] Introduction
A reasonable objection to a state of affairs is to object to or refuse to agree to carry out a particular task under instructions or an order – and having valid reasons for doing so. For example, a person may object to being ordered to fight for their country on the grounds of being a pacifist.
[edit] Construction
In construction, risks abound and, in many cases, it is the contractor who has to shoulder them. Typically, contractors face risks such as:
- Unknown or unknowable ground conditions.
- Delays not requiring an extension of time, e.g weather-related.
- Responsibilities for surveying previous work or existing structures.
- The construction process generally.
- Major variations.
- The work of consultants subcontractors and suppliers.
This is why some contracts and sub-contracts (such as JCT contracts) can, in certain circumstances, allow the contractor / subcontracator to raise an objection, such as to a variation order, if they have reasonable grounds.
A typical example might be where the client (employer) selects a sub-contractor with particular expertise, while leaving responsibility for their performance with the main contractor. Where the selected subcontractor was not pre-named in the contract (and is therefore now post-named) the contractor is able to raise reasonable objection within a certain time limit (often 7 days).
The grounds upon which a contractor may raise reasonable objection include:
- The specialist has a poor safety record.
- There are reasonable grounds for believing that the specialist may not be financially secure, solvent, reliable or technically competent.
- The tender sum is not believed to be financially viable.
- The programme is deemed to be unreasonable.
In the past, substantial variations that have changed the identity of the contract or even negated it completely have given contractors the right to reasonable objection, if an additional sum for the works could not be agreed on. However, this may no longer be as certain to succeed, thanks to a legal precedent from the 1990s.
In McAlpine Humberoak Limited v McDermott International, [1992] it was established that even in a situation where the extra works involved substantial changes, they did not necessarily alter or transform the identity of the contract. Therefore, the contractor (in this case for an offshore installation) was bound to the original contract and the objection overruled.
The 2016 JCT Standard Building Contract Without Quantities, clause 5.1.2, made clear that the right of reasonable objection relates to employers making changes to:
- Site access.
- Limitations on working space.
- Limitations on working hours.
- Changes to the specific order of the works.
Clause 5.1.1, made clear that the following allow a right of reasonable objection:
- Changes to the design, quality or quantity of the works.
- Changes to the kind or standard of materials or goods.
- Removal from the site of work or materials that are not defective.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Installing solar panels on listed structures.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.
ECA learning zone and industry focus video series
From updates and amendments to circular economy, emergency lighting and much more.