Reasonable objection
[edit] Introduction
A reasonable objection to a state of affairs is to object to or refuse to agree to carry out a particular task under instructions or an order – and having valid reasons for doing so. For example, a person may object to being ordered to fight for their country on the grounds of being a pacifist.
[edit] Construction
In construction, risks abound and, in many cases, it is the contractor who has to shoulder them. Typically, contractors face risks such as:
- Unknown or unknowable ground conditions.
- Delays not requiring an extension of time, e.g weather-related.
- Responsibilities for surveying previous work or existing structures.
- The construction process generally.
- Major variations.
- The work of consultants subcontractors and suppliers.
This is why some contracts and sub-contracts (such as JCT contracts) can, in certain circumstances, allow the contractor / subcontracator to raise an objection, such as to a variation order, if they have reasonable grounds.
A typical example might be where the client (employer) selects a sub-contractor with particular expertise, while leaving responsibility for their performance with the main contractor. Where the selected subcontractor was not pre-named in the contract (and is therefore now post-named) the contractor is able to raise reasonable objection within a certain time limit (often 7 days).
The grounds upon which a contractor may raise reasonable objection include:
- The specialist has a poor safety record.
- There are reasonable grounds for believing that the specialist may not be financially secure, solvent, reliable or technically competent.
- The tender sum is not believed to be financially viable.
- The programme is deemed to be unreasonable.
In the past, substantial variations that have changed the identity of the contract or even negated it completely have given contractors the right to reasonable objection, if an additional sum for the works could not be agreed on. However, this may no longer be as certain to succeed, thanks to a legal precedent from the 1990s.
In McAlpine Humberoak Limited v McDermott International, [1992] it was established that even in a situation where the extra works involved substantial changes, they did not necessarily alter or transform the identity of the contract. Therefore, the contractor (in this case for an offshore installation) was bound to the original contract and the objection overruled.
The 2016 JCT Standard Building Contract Without Quantities, clause 5.1.2, made clear that the right of reasonable objection relates to employers making changes to:
- Site access.
- Limitations on working space.
- Limitations on working hours.
- Changes to the specific order of the works.
Clause 5.1.1, made clear that the following allow a right of reasonable objection:
- Changes to the design, quality or quantity of the works.
- Changes to the kind or standard of materials or goods.
- Removal from the site of work or materials that are not defective.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February