Attendance for construction
Attendance is the main contractor’s mark up for specific services it has to provide for individual suppliers or sub-contractors. This might include items such as material handling, scaffolding and rubbish clearance.
Attendance can be ‘general’ or ‘special’.
General attendance is the description of main contractor attendance available site wide to all suppliers or sub-contractors such as:
- Welfare facilities.
- External scaffolding.
- Temporary power and lighting.
- Platform and passenger hoists.
- Tower crane lifts by prior arrangement.
- Site security.
- Waste disposal.
Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor, such as:
- Special hoists.
- Builders work such as a concrete plinth.
- Special scaffolding.
It is important to establish within the contract documents whether items that suppliers or sub-contractors require will constitute attendances that will be provided by the main contractor, or whether they will provide them themselves (such as their own specialist equipment).
Attendance should not be confused with general site preliminaries or builder’s work in connection with mechanical and electrical services. These items are separately priced.
[edit] Related articles on Designing Buildings
Featured articles and news
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.