[edit] Introduction
Hoists are used on construction sites to vertically transport materials and/or passengers. They are most commonly powered by diesel engines or electric motors that rotate a drum around which a wire rope is wound. Hoists may also be hydraulically powered, and may use chains as the lifting mechanism rather than wire rope.
The landing area must be fitted with some form of guard, usually sliding gates, and the base of the hoist, where the winch is situated, should be well guarded to prevent injury. There must be a risk assessment undertaken prior to hoisting, and subsequent lifting operations should be properly planned and carried out in accordance with the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER).
Hoists differ from cranes in that cranes move items vertically and horizontally. Hoists differ from lifts in that they are generally used for industrial purposes and are not publicly accessible. Winches are typically used to pull or drag items along level surfaces, rather than lifting them vertically.
[edit] Mobile hoists
Mobile hoists are commonly found on construction sites, and are capable of lifting material loads to heights of up to 30 m. They are designed to be dismantled, folded onto the chassis and moved to another location with relative ease, either under their own power or towed by a haulage vehicle.
The mast and winch unit is mounted on a platform, typically with a load capacity of 500 kg. This is then stabilised using jacks or outriggers. Extending upwards, a lattice hoist mast is constructed to which sections can be added depending on the height required, together with tie supports fixed to scaffolding or the building frame. A protective screen is placed around the hoist mast, fitted with gates at least 2 m high at all landing levels.
[edit] Passenger hoists
These are designed to lift passengers, although they can also be used for materials as long as the weight is kept within the loading capacity. The type of hoist can vary from a single cage with rope suspension to twin cages with rack and pinion operation mounted on two sides of a static tower. They are usually controlled from within the cage, and there must be additional safety devices to prevent over-run or free-fall.
A typical passenger hoist cage is 2.7 m high and capable of carrying 12 passengers at a total weight of 1,000 kg. Typical speeds are 40-100 m/min. The hoist tower is generally assembled from 1.5 m-long sections and tied at 12 m centres to the face of the structure.
[edit] Small package hoists
Small hoists consisting of a small lifting arm, simple electric motor and wire rope can be bolted to a structure or to scaffolding and used for light-lifting operations of around 500kg.
[edit] Related articles on Designing Buildings
- Bituminous mixing and laying plant.
- BS 7883.
- BS 7883 guide released.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Construction tools.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Equipment in buildings.
- Excavating plant.
- Fall arrest system.
- Firefighting lift.
- Forklift truck.
- Gantry.
- How to use a ladder.
- Lifting device.
- Lifting platform.
- Lifting sling.
- Lifts for buildings.
- Lifts for office buildings.
- Pallet jack.
- Scaffolding.
- Stairs.
- Temporary works.
- Tremie.
- Types of cranes.
- Types of scaffolding.
- Winch.
- Work at height regulations.
[edit] External references
- ‘Introduction to Civil Engineering Construction’ (3rd ed.), HOLMES, R., The College of Estate Management, (1995)
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann, (2007)
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.