Material handling in construction
In the construction industry, the term 'material handling' refers to the delivery, movement, storage and control of materials and other products. This forms part of the logistics management of a project.
Types of plant used for material handling on site include; hydraulic excavators, telescopic handlers, cranes, forklift trucks, lifting devices, conveyor systems and so on.
From receipt and inspection of materials, through to storage, assembly and use, the material handling system should be well-coordinated and organised so that everyone on site is aware of how it works. When handling materials, safety should be the primary consideration. Pre-start inspections are critical, load limits should not be exceeded, method statements should be followed, and it may be necessary for a banksman to direct material movements around the site.
It is important to follow best practice guidelines when designing a material handling system for a construction project. For example:
- The proposed system of material handling should be defined in terms of needs, objectives and functional specification.
- Methods and processes should be standardised to avoid confusion.
- Unnecessary handling or movement should be reduced or eliminated.
- Working conditions and methods should have worker safety as the primary objective.
- Unit loads should be optimised, to reduce work and risk.
- Storage areas should be kept organised and clean, maximising density as much as possible and eliminating damage to materials.
- Sites should be kept safe, clean and easy to move around.
- Deliveries should be received and handled promptly.
- Site waste management plans should be created and maintained.
- Automated material handling technologies should be used where practicable.
- Safety equipment such as PPE should be available.
Incorrect manual handling is a common factor in work-related injuries. This can be because of:
- The weight of the item being handled.
- The repetitive nature of the movement.
- The distance the item is being moved.
- Where the item is being moved to and from.
- The posture of the individual. Any twisting, bending, stretching or other awkward position may exacerbate problems.
The Manual Handling Operations Regulations place obligations on employers to manage the risks of manual handling to their employees. For more information see: Manual handling.
[edit] Related articles on Designing Buildings Wiki
- Construction materials.
- Construction plant.
- Don’t run short of materials on your construction project
- How to manage construction plant.
- Logistics management.
- Manual handling.
- Materials on site.
- Off site materials.
- Protecting and storing rebar.
- Quality control.
- Resource management plan.
- Site storage.
- Site Waste Management Plan.
Featured articles and news
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
Good points, we wrote a similar guide but aimed more specifically at the groundworks sector: https://www.sitestak.co.uk/news/how-to-store-pvc-drainage-materials-and-pipe-prior-to-installation