Resource management in construction
[edit] What is resource management in construction?
The UK construction industry is the largest consumer of resources, requiring more than 400 million tonnes of material a year (ref. Davis Langdon). In addition, more than 2 million people are employed in the construction industry.
Construction companies face the challenge of delivering complex projects to a schedule, complying with the client's specification, within a budget, and with a reasonable profit margin. Resource management is the process of planning the supply and management of the resources necessary to satisfy the client’s requirements. on time and to budget. Proper resource management ensures that resource demand is satisfied and that the benefit derived from resources is maximised.
Fundamental to effective resource management is a clear understanding of what resources are needed, what resources are available, where resources are located, and the ability to schedule those resources accordingly.
Resource management may involve more than one project, ensuring that the use of resources is optimised between projects. This may lead to conflicts, where the resources required to optimise delivery of a single project are not the same as the resource allocation that will optimise performance across a portfolio of projects.
Without proper resource management, projects can fall behind schedule, or can become unprofitable. In extreme circumstances, the resources required may simply not be available, and alternatives will have to be sought.
[edit] What resources are required on construction projects?
Construction resources might include:
- Products and materials.
- Construction plant, tools and equipment.
- Human resources.
- Space and facilities.
- Subcontractors.
- Finances.
[edit] The benefit of preparing a resource management plan
A resource management plan can be used to:
- Ensure resource availability and resolve resource conflicts.
- Optimise time, effort and cost.
- Ensure workers with the right skills are available at the right time and location.
- Identify limitations, such as site access, weather conditions, and so on.
- Reassign resources in response to circumstances.
- Track resources utilisation to avoid excessive resourcing or under-utilisation.
A resource management plan should list key information about the required resources for each activity:
- Type of activity.
- Start date and duration of the activity.
- Responsible owner for activity.
- Resource type and quantity.
- Source and supplier of each resource.
- Equipment required to use resource.
- Cost estimates for each of the resources to be supplied.
- Waste management.
- Risk mitigation.
[edit] How to develop a successful resource management plan
Successful resource management requires:
- Access to an up-to-date project plan with clear definition of the different phases of work and activity scheduling.
- Understanding of the types of resources that are needed.
- Understanding of the availability and optimum utilisation of resources.
- Understanding of the potential for developing resources for new uses.
- Understanding of the lead time required to ensure that resources are available when needed.
- The ability to redeploy resources if works need to be accelerated, or when works are completed.
[edit] What is automated resource management?
Automated, or partially automated resource management systems can improve companies’ overall efficiency, replacing less efficient data collection methods such as paper forms, spreadsheets, and so on.
Some of the features that automated resource management systems can incorporate include:
- Automated calculations.
- Ability for managers to simulate and test different scenarios.
- Re-evaluation and re-calculation as decisions change.
- Real-time resource utilisation tracking.
- Resource allocations can be assessed anywhere and approved quickly online.
- Online collaboration between sites, offices, partners, subcontractors, and so on.
[edit] Acceleration of construction
It may become necessary to accelerate the progress of works, either to achieve the completion date, or to meet a new requirement imposed by the client (such as accommodating additional works, or bringing the completion date forward). Typically, this will require that additional resources are used, although it might be achieved by a reduction in scope of other works, or changes to the design.
See Acceleration for more information.
[edit] Fast track construction
Fast-track construction is a scheduling technique that can be used to reduce the overall duration of projects by overlapping tasks that on a traditional contract would not be commenced until the previous task was completed. Whilst the same number of tasks need to be performed, they are condensed into a shorter period, and so are likely to require more resources.
See Fast track construction for more information
[edit] Resource levelling
Resource levelling is a project management technique in which the demand for limited resources is accommodated by adjusting the project programme. In construction, resource levelling can be used to analyse the variations in resource usage that can occur over time, and which can be inefficient and costly.
See Resource levelling for more information.
[edit] Human resource management
Human resource management (HRM) is the process of managing people within an organisation. In construction, HRM is primarily concerned with ensuring that a project has sufficient human resources, with the correct skill-sets and experience, for the project to be successfully completed.
See Human resource management for more information.
[edit] Waste management
32% of landfill waste comes from the construction and demolition of buildings and 13% of products delivered to construction sites are sent directly to landfill without being used (ref. Technology Strategy Board).
Effective waste management is becoming increasingly important on construction projects, ensuring that waste is properly and efficiently handled, and ideally that it is minimised, re-used, or recycled. Ideally, a site waste management plan (SWMP) should be prepared before construction begins, describing how materials will be managed efficiently and disposed of legally during the construction of the works, and explaining how the re-use and recycling of materials will be maximised.
For more information see: Site waste management plan.
[edit] Related articles on Designing Buildings
- Acceleration of construction works.
- Activity schedule.
- Agile.
- Construction inventory management.
- Construction logistics manager.
- How to manage construction plant.
- Logistics management.
- Programme for building design and construction.
- Resource allocation in design and construction.
- Resource levelling.
- Scheduling construction activities.
- Time-location chart.
- Time management.
- Time management of construction projects.
- Understanding agile in project management.
Featured articles and news
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
To make a comment about this article, click 'Add a comment' above.
Separate your comments from any existing comments by inserting a horizontal line.
Resource management is one of the hardest things to get right - the amount of waste in the industry is terrible.