Milestones
Milestones are important project management tools that can be used as a component of project scheduling.
A milestone is a significant event that occurs during the course of a project, the timing of which can influence the scheduling of other activities. With the achievement of successive milestones, management is able to maintain a more accurate understanding of how the project is advancing according to the schedules.
Milestones might include, for example:
- Securing funding.
- Acquiring a site.
- Appointing consultants.
- Completing design stages.
- Client approvals.
- Securing permissions.
- Tendering the construction contract.
- Appointing a contractor.
- Handing over the site to the contractor.
- Starting and completing construction.
- Occupying the completed development.
- Rectifying defects.
Milestones are a feature of many project management software tools and often appear on Gantt charts, represented by diamond symbols. Developing schedule with milestones marked along a project programme can help give clarity to a timeline which can otherwise be very complex and difficult to interpret. This can be particularly useful for some stakeholders who may only need a very general understanding of a project programme.
They may coincide with key decisions or gateways at which the client assesses the state of development of the project and considers whether to progress to the next stage. However, it is important that milestones are allocated to the achievement of a task, not to the task itself.
For example, consultants often describe client decisions as milestones on project programmes, when in fact, the client may need to be provided with information to make a decision, they need time to consider that information, and they may then need to convene a meeting, which if they are senior personnel may only be possible on specific dates (such as at pre-planned board meetings).
Milestones are known as a ‘task of zero duration’ because they represent a particular point of time in a project when an achievement has been reached, they do not represent the activities necessary to complete a task.
They are often used to show progress on critical rather than non-critical activities, that is, items that represent a potential ‘bottleneck’ in the progress of a project. The overall critical path for a project represents the shortest time in which the project can be completed. Achieving milestones on the critical path more quickly than was planned will reduce the overall project programme.
However, this can serve to present a misleading impression of the overall health of the project, as project managers may prioritise resources into achieving critical milestones, whilst neglecting those works that are not identified as a milestone. This can change the critical path so that activities which were not previously critical become so.
To be useful tools in monitoring and controlling a project, project managers must be careful not to overuse milestones as a means of driving progress, whilst ensuring there is no loss in momentum as a result of spacing milestones too far apart. Instead, a compromise must be reached with milestones pinpointing suitably critical deliverables on a consistent basis, commonly at intervals of no longer than every fortnight for projects of several months duration.
Suitable remedies must be planned in the event that a milestone is missed. Resources may need to be reallocated to ensure they continue to be matched to priorities. However, it is important that milestones represent a challenge and should be treated as opportunities to make adjustments as the work is proceeding.
See also: Milestone payment.
[edit] Related articles
- Acceleration of construction works.
- Activity schedule.
- Benefits realisation milestone.
- Change control procedures.
- Contractor’s master programme.
- Critical path method.
- Data drops.
- Gantt chart.
- Gateways.
- How progress is agreed in construction.
- Key dates.
- Key performance indicators.
- Line of balance (LOB).
- Milestone payment.
- Pareto analysis.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Progress of construction works.
- Project crashing.
- Project manager.
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Transition point.
[edit] External references
Featured articles and news
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA has launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.