What approvals are needed before construction begins
Contents |
[edit] Introduction
Construction works can be complex, impacting on a large number of people, and having significant health and safety and other wider implications. As a result, a number of approvals may be required before construction works begin. Generally, the number of approvals required will increase with the size, complexity and sensitivity of the proposed works.
[edit] Planning permission
Construction works may need planning permission before they begin. The is the granting of permission to proceed with a proposed development. Responsibility for granting permission generally lies with local planning authorities (usually the planning department of the district or borough council). All developments require planning permission, other than ‘permitted developments’, which are considered to have insignificant impact.
Planning conditions or planning obligations can be imposed on planning permissions, and these may need to be discharged before construction works begin. If an outline permission is granted, then reserve matters approvals may be required.
Local planning authorities have the power to charge the community infrastructure levy (CIL) on new developments to fund local infrastructure. A commencement notice must be submitted at least one day before the works begin, and the local authority will then issue a demand notice which will set out the payments required. See: Community infrastructure levy commencement notice.
NB: In Scotland, Regulation 37 of the 1997 Act requires that developers must, as soon as practicable after deciding a date on which to start a development, and in any event before commencing the development, give notice to the planning authority.
The planning authority may require additional submissions, such as a site waste management plan, environmental impact assessment and so on.
For more information, see Planning permission.
[edit] Building regulations approval
Construction works may also need building regulations approval. The building regulations set out requirements for specific aspects of building design and construction. Building regulations approvals can be sought either from the building control department of the local authority or from an approved inspector.
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works begin. On small projects, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
A separate notice will generally be required by the building control body, telling them when construction works are going to begin. There may also be additional information required by the building control body before construction begins, such as the target emission rate and building emission rate (or dwelling emission rate). For more information see Target emission rate.
All residential buildings (new and existing) that are 18m tall or higher, or at least seven storeys tall (referred to as higher-risk buildings) must be registered with the Building Safety Regulator (BSR) providing relevant information about the building, Since the introduction of the Building Safety Act 2022, BSR is the building control body for higher-risk buildings.
For more information, see Building regulations, Building Safety Regulator, higher-risk buildings and the Building Safety Act 2022
[edit] Health and safety
The Construction (Design and Management) Regulations (CDM Regulations) ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. The regulations require that the Health and Safety Executive (HSE) is notified if construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or exceed 500 person days.
The client must submit the notice (F10 - Notification of construction project) as soon as practicable before construction begins, or arrange for someone else do this on their behalf. The client must ensure that an up-to-date copy of the notice is displayed in the construction site office so that it is accessible to anyone working on the site in a form that can be easily understood.
For more information, see CDM.
[edit] Party Wall Act
The Party Wall etc. Act 1996 grants the owner of a property the right to undertake certain works that might otherwise constitute trespass or nuisance. It also protects the interests of adjoining owners from any potentially adverse effects that such works might have by imposing a requirement that all adjoining owners are given prior notice.
Such notice must be served where the owner of a property intends to erect a new wall at a boundary, carry out works to party structures, or carry out excavations up to 6 m away from a building or structure on neighbouring land.
For more information, see Party Wall Act.
[edit] Environmental consents
Consent may be required from the Environment Agency or the local authority for works that could; pollute the air, water or land, increase flood risk or adversely affect land drainage.
For more information, see Environment Agency guidance.
[edit] Other approvals
Other approvals that might be required could include:
- Advertisement consent.
- Certificate of established use.
- Certificate of immunity from listing.
- Designated areas.
- Felling or lopping a tree.
- Hazardous substances consent.
- Lawful development certificates.
- Listed building consent.
- Mining or working of minerals.
- Notification where the Crown is developing on Crown-owned land.
- Scheduled monument consent.
- Highway works licences (such as stopping up roads, removal of parking, obstructions to pavements, skip parking and hoarding).
- River works.
- Nuclear works.
- Works affecting a railway.
Permissions for certain types of use may be required under the Licensing Act or Gambling Act.
It can also be wise to inform other bodies that work is going to begin, particularly on large projects:
- Emergency services.
- Utility providers.
- Post office.
- Neighbours.
- Suppliers and subcontractors.
- Insurers.
- Landlords or tenants.
- Funders.
- Telecom provider.
[edit] Related articles on Designing Buildings
- Adjoining owner.
- Alterations to listed buildings guidance note.
- Approve.
- Approval of conditions on a planning permission.
- Building regulations.
- Commencement.
- Community infrastructure levy.
- Community infrastructure levy commencement notice.
- Commencement.
- Construction covered by the Party Wall Act of 1996.
- Easements.
- Environmental legislation.
- Full plans.
- Licensing.
- Line of junction notice.
- Listed buildings.
- Mobilisation.
- Party Wall Act.
- Planning permission.
- Restrictive covenants.
- Rights to light.
- Scheduled monuments.
- Statutory authorities.
- Statutory obligations.
- Statutory undertakers.
- Tree preservation orders.
- Tree rights.
Featured articles and news
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
NBS launches industry guide for specification writing
Available for free and as immediate download.
Peter Barber’s work revives forgotten building types.
Insights of how to attract more young people to construction
Results from CIOB survey of 16-24 year olds and parents.
Focussing on the practical implementation of electrification.
Preston flood scheme completes primary school SuDS
Three primary schools benefit from SuDS schemes.