Reserved matters in planning permissions
Outline planning applications can be used to find out whether a proposed development is likely to be approved by the planning authority, before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage.
Reserved matters, also refers certain matters concerning the governance of the UK, where decisions may be taken by the UK Parliament at Westminster even though they have an effect in Scotland, Wales, Northern Ireland or the regions of England. Such reserved matters may also give allowance for devolved governments to implement slightly different regimes, though more directly, where matters are accepted areas where decision-making has been delegated by Parliament to the devolved institutions such as the Scottish Parliament, the Assemblies of Wales, Northern Ireland and London or to Local Authorities, these are referred to as devolved matters.
In terms of reserved matters and outline planning applications on the 10 August 2006, changes to the outline planning permission process came into force intended to make outline planning applications more 'detailed' and so to restrict the extent of reserved matters. Reserved matters that might be the subject of further applications once outline planning consent has been obtained can now include:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed in any way.
Outline permission is not a permission to start work on site. The permission notice will state which matters have been reserved for later approval. When all of the reserved matters have been approved, work may begin on the site.
Reserved matters applications should be submitted within 3 years of outline permission being granted.
Outline planning permission lasts for two years from the date reserved matters were approved, or three years from the date of the outline planning permission, whichever is the later.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
If a reserved matters application in respect of a new road junction from a possible new housing development onto the main highway is unsupported by Highways England, on the grounds of unachievable visibility splay distances, must the Local Authority then turn down that application? What then happens to the original planning application for that access road, which was previously approved?