Reserved matters in planning permissions
Outline planning applications can be used to find out whether a proposed development is likely to be approved by the planning authority, before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage.
Reserved matters, also refers certain matters concerning the governance of the UK, where decisions may be taken by the UK Parliament at Westminster even though they have an effect in Scotland, Wales, Northern Ireland or the regions of England. Such reserved matters may also give allowance for devolved governments to implement slightly different regimes, though more directly, where matters are accepted areas where decision-making has been delegated by Parliament to the devolved institutions such as the Scottish Parliament, the Assemblies of Wales, Northern Ireland and London or to Local Authorities, these are referred to as devolved matters.
In terms of reserved matters and outline planning applications on the 10 August 2006, changes to the outline planning permission process came into force intended to make outline planning applications more 'detailed' and so to restrict the extent of reserved matters. Reserved matters that might be the subject of further applications once outline planning consent has been obtained can now include:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed in any way.
Outline permission is not a permission to start work on site. The permission notice will state which matters have been reserved for later approval. When all of the reserved matters have been approved, work may begin on the site.
Reserved matters applications should be submitted within 3 years of outline permission being granted.
Outline planning permission lasts for two years from the date reserved matters were approved, or three years from the date of the outline planning permission, whichever is the later.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Installing solar panels on listed structures.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.
ECA learning zone and industry focus video series
From updates and amendments to circular economy, emergency lighting and much more.
The Building People Communities Network
Celebrating and amplifying voices of the under-represented, this refugee week and pride month.
Pride of Place: queer heritage
Acknowledging and taking pride in LGBTQ histories.
Comments
If a reserved matters application in respect of a new road junction from a possible new housing development onto the main highway is unsupported by Highways England, on the grounds of unachievable visibility splay distances, must the Local Authority then turn down that application? What then happens to the original planning application for that access road, which was previously approved?