Notifiable project F10 form
The Construction (Design and Management) Regulations 2015 (CDM regulations) require that the Health and Safety Executive (HSE) must be notified of any project defined as construction under the regulations where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or exceed 500 person days. This can be done using an F10 form.
Regulation 6 of the CDM regulations requires that the client must give notice in writing to the HSE as soon as is practicable before the construction phase begins, or arrange for someone else to do this on their behalf.
The notice must include the details included in schedule 1 of the regulations:
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the construction site is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
Where details are not available (such as the details of the principal contractor) they must be provided when they are available, and in any event, before construction works begin.
The notice must also be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and if necessary, be periodically updated.
HSE will take 10 days to process notifications by manual form. (Ref. HSE, F10 Manual input form frequently asked questions.) However, notification can now be carried out online by filling out an e-form and manual notification forms will cease to be available after 31 March 2015. Confirmation of receipt of an e-F10 form should be received shortly after submission.
[edit] Related articles on Designing Buildings
- Accident book.
- Accident report.
- CDM.
- CDM for self-builders and domestic clients.
- Competent person.
- Fee for intervention.
- First aider.
- Health and safety.
- Health and Safety Executive.
- Health and safety inspector.
- Incident reporting system.
- Inspections focus on occupational lung disease.
- Licence for Alterations for Apartment.
- Principal contractor.
- Reporting accidents and injuries on construction sites.
- Site records and registers.
- What approvals are needed before construction begins.
[edit] External references.
- HSE How to notify a project.
- Schedule 1 of the CDM regulations.
Featured articles and news
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Key points and relevance to construction of meeting, due to reconvene.
Comments