Estimate
The term ‘estimate’ is a very broad one that refers to any activity that attempts to quantify something. In the construction industry, it is typically used in relation to the approximate costs associated with a construction project, used, for example to assess the viability or affordability of the project or aspects of it.
An estimate is an attempt to predict the likely expenditures associated with a project as accurately as possible. The degree of detail and the accuracy of estimates will typically increase as the project progresses, more decisions have been made, and more information is available, however, their true accuracy only becomes apparent once the project is complete and the actual costs incurred.
At the outset, estimates may be made to help determine whether a project is affordable and to set a budget. They will then be used to test design options to ensure they are in line with the budget.
A pre-tender estimate (PTE) is a final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers.
Contractors, subcontractors and suppliers will then prepare definitive cost estimates to submit tenders in the construction bidding process to compete for the award of contracts.
There are a number of methods available for estimating, depending on the stage of the project and the information available:
- Benchmarking, which is a process by which other similar projects are used as comparisons.
- Breaking down an overall estimated construction cost into percentages for different elements, based on the experience of the cost consultant.
- Measuring defined quantities from drawings.
For more information see: Types of estimating.
Initial cost estimates might include wider project costs that the client might incur, such as; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on. Later in the project, estimates are likely to focus on the construction cost of the project. It is important to be clear therefore what costs are being included in estimates, and estimates might be accompanied by a schedule of the assumptions that have been made.
Estimates will generally include contingencies, which are downside risk estimates that make allowance for unknown risks associated with a project. At the preliminary business plan stage, estimates might include a 15% contingency, but this may then be reduced as the project progresses and risks pass.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines estimate as: A prediction or forecast of the resources (i.e. time, cost, materials, etc.) required to achieve or obtain an agreed scope of work (i.e. for an investment, activity, project, etc.).’
[edit] Related articles on Designing Buildings
- Analogous estimating.
- Base cost estimate.
- Benchmarking.
- Bottom-up estimation.
- Budget.
- Building works estimate.
- Cash flow projection.
- Common mistakes in bill of quantities.
- Contingencies.
- Cost overruns.
- Cost plans.
- Elemental estimating.
- Elemental method.
- Estimator.
- Expert opinion estimating.
- Extra over (EO).
- Initial cost appraisal.
- Irrelevant cost.
- Operational rate estimate?.
- Order of cost estimating.
- Parametric estimating.
- Post tender estimate.
- Pre-tender estimate.
- Spon's Price Book.
- Tender pricing document.
- Three point estimation.
- Top down estimating.
- Types of estimating.
- Unit rate estimating.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Preparing for the future: how specifiers can lead the way
Effective specificationand the Future Homes Standard.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.