Cost overruns in construction
In construction, cost overruns are relatively common, occurring when the costs being incurred are in excess of the amounts that have been budgeted for.
There are a number of possible reasons for this:
- Construction contracts are often tendered and won on the basis of the lowest cost bid. Costs can then increase as contractors attempt to claw back some profit.
- Construction projects are complex, involving a large number of different parties, components, requirements and other factors.
- Projects can take a long time to complete, during which costs may change.
- Deficiencies and inaccuracies in design.
- Poor project management.
- Changes in client requirements.
- Unforeseen costs that only become apparent as the works progress.
- Poor communication between project team members.
- Tools, equipment and plant being unavailable, in poor condition, etc.
- Skilled workers being unavailable.
- Inaccurate cost information that leads to incorrect pricing (e.g. material prices).
- Adverse site or ground conditions.
- Late or withheld payments.
- Scope creep.
The different ways in which cost overrun can be described include:
- As a percentage of the total cost.
- As a total percentage including the original budget and the overrun amount.
- As a percentage of the cost overruns to the original budget.
In order to address and manage cost overruns, it is important to identify what the root causes are. While specific events such as extreme weather conditions can cause delays or damage which may result in cost overruns, they are often the result of more complex project management issues that can be difficult to untangle.
The largest cost overruns tend to occur due to a change in requirements. If, for example, the client needs a space to be 20% larger than originally anticipated, then the cost is likely to increase by at least 20%. It is very important therefore to ensure that the project brief is comprehensive and that all project stakeholders accept it and agree on the specific scope of work and performance requirements.
Pre-construction estimates and careful project planning are then vital in terms of ensuring accuracy and confidence in the project costings, particularly if the project is complex and has the potential to change.
Design and construction issues can be mitigated in some cases by using project-wide project management, cost control software or building information modelling (BIM) as a way of ensuring all stakeholders are using the same up-to-date design information, as well as being able to make real-time adjustments.
Change orders may also be a reason for costs overrunning. A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original contract amount and/or completion date.
If one of the parties to a contract fails to perform as required by the contract, and this results in costs overrunning, it may constitute a breach of contract. A breach of contract may entitle the innocent party to make a claim for damages for the losses it has suffered.
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.