Initial cost appraisal for design and construction
Initial cost appraisals are carried out without the benefit of a design for the project. They include client costs that may not feature in later cost plans and as a result will almost certainly need input from the client's finance director or financial advisers.
Once the initial cost appraisal is completed, the client will decide the scope of costs that will in future be monitored by the cost consultant and those that will be monitored and controlled by the client organisation.
Initial cost appraisals break down the overall project budget based on information provided by the client, an analysis of comparable projects and the experience of the cost consultant.
Initial cost appraisals might include:
- Assumptions about the nature of the project, identifying variables. This will include a guestimate of gross internal floor area and a rate psm to be applied from a range of historical data. Repetition with standard solutions carries with it cost efficient options. For more information, see Cost of building.
- Inclusions and exclusions.
- Look at location and site constraints. Central London will attract a premium. Ground conditions and proximity of neighbouring buildings affect costs.
- Adjust for market conditions.
- The building's function and facilities influence design loadings, floor to floor heights and structural spans which may affect costs. Special spaces with acoustic or vibration control will attract a premium.
- State the procurement route as an assumption.
- Land costs and purchase prices.
- Book value.
- Legal fees (including vendor).
- Agent fees (including vendor).
- Stamp duty.
- Site investigations and surveys.
- Demolition.
- Consultant team fees including expenses and unusual items such as models.
- Running costs.
- Building and infrastructure costs. At this stage building and infrastructure costs should be set on an overall unit basis, based on comparable projects, with assumptions relating to different types of areas and abnormal items. Units costs could include the number of; dwelling units, parking spaces, rentable area, hotel bedrooms, hospital beds, prison cells, and so on.
- Fixtures, fittings and equipment.
- Relocation / migration costs.
- Promotion and marketing.
- Capital gains tax.
- Corporation tax.
- Irrevocable VAT.
- Planning fees.
- Building control fees.
- Void costs.
- Insurance.
- Establishment costs.
- Funding costs.
- Capital allowances.
- Grants.
- Inflation escalation.
- Operational and whole-life cycle costs.
- Allocation of contingencies sum.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bid strategies.
- Bills of quantities.
- Budget.
- Business plan.
- Common arrangement of work sections.
- Contract sum.
- Contract sum analysis.
- Cost-benefit analysis in construction.
- Cost consultant.
- Cost information.
- Cost overruns.
- Cost plans.
- Elemental cost plan.
- Estimate.
- Final account.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender pricing document.
- Whole-life costs.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.