Escalation
Civil Engineering Procedure, 7th edition, published by the Institution of Civil Engineers (ICE) defines ‘escalation’ as an: 'Increases (or decreases) in the costs of labour or materials due to inflation (or recession and deflation).'
Some contracts make provisions for contract price adjustment to allow for the effects of escalation based on data about changes in the cost of commodities, labour, fuel and so on. Such allowances might be referred to as ‘fluctuations’ as there is a fluctuating price in the contract (although fluctuations generally also allow for changes in taxation and increases in head office or administrative costs).
On smaller projects of a short duration, the contractor may be expected to have taken the effects of escalation into account when calculating their price, and they may be able to hold sub-contractors and suppliers to agreed prices for the duration of the contract.
On larger projects, typically lasting more than a year, the contractor may be asked to tender based on prices at an agreed base date, and then the contract makes provisions for escalation to specified items over the duration of the project, such as fuel, steel and so on.
Determining the actual amount of escalation for each item would be very time consuming, and so calculations are generally based on agreed indices, such as public records, JCT bulletins and so on.
Escalation can be caused by issues such as:
- An overheating construction industry.
- Natural disasters.
- Exchange rate changes.
- Changes to regulations.
- Supply problems.
- Labour shortages.
- Inflation in the wider economy, such as fuel price increases or wage increases.
- Global economic conditions.
Escalation clauses put the client at risk, as the final price is not known when the contract is agreed. It is sensible therefore for clients to forecast likely escalation during the course of the project and to make allowances for this, with a contingency provision.
Significant escalation which has not been allowed for can result in the scope of projects being reduced, and can even bring projects to a halt.
However, if there were no escalation provisions, the contractor would have to bear all the risk of price changes, and this would be reflected in their tender.
NB ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines escalation as: ‘A positive or negative factor or rate reflecting an estimate of differential increase/decrease in the general price level for a particular commodity, or group of commodities, or resources (ISO 15686-5).’
See also: Escalation clause and Fluctuations.
[edit] Related articles on Designing Buildings
Featured articles and news
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese as well as English.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.