Building notice for building regulations approval
There are two ways of obtaining building regulations approval:
- A full plans application, and
- A building notice application.
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out. On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
A building notice application can be made with a simple application form, a site plan (if an extension is involved) and the appropriate fee (calculations may also be required for certain aspects depending on the complexity of the project). This means that work can begin very quickly, and need not necessarily involve design consultants.
However, a building notice application leaves the client at risk that completed works might not be approved, resulting in remedial costs. Clients should be certain that their builder is familiar with all the relevant regulations before deciding to follow this route. It is also worth considering that proceeding without a full set of agreed drawings is more likely to result in disputes.
Building control fees for a building notice may be more expensive than for a full plans application.
Building notices cannot be used:
- For building work to which the Regulatory Reform (Fire Safety) Order 2005 applies (generally commercial or industrial buildings).
- For building work close to, or over the top of rain water or foul drains.
- Where a new building will front onto a private street.
Inspections must be arranged in advance by giving notice to the building control inspector. Notice is likely to be required at:
- Commencement.
- Excavation for a foundation, before covering up.
- Foundations, before covering up.
- Damp proof course, before covering up.
- Concrete or other material laid over the site, before covering up.
- Drains.
- Structural timbers, steelwork or concrete, before covering up.
- Completion.
Other inspections may be deemed necessary by the inspector.
If the local authority is not given notice of work for inspection it may require that the work is opened up for inspection.
If the local authority believes the building work contravenes the building regulations, they may serve an enforcement notice requiring alteration or removal of the work that contravenes the regulations. It is not possible to ask for a determination (appeal) of an enforcement notice as there are no drawings upon which a determination could be made.
A building notice is valid for three years after which it will automatically lapse if the building work has not begun.
It is important to ensure that a completion certificate is sought as evidence that the works comply with the regulations. Under changes to the building regulations made in December 2012, Local Authorities must give completion certificates, they should not need to be requested.
NB: Full plans approvals are also subject to inspection during the course of the works, but as long as the work is carried out in accordance with the approved design, the risk of problems is very much lower than for a building notice application.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.