How progress is agreed in construction
Contents |
[edit] Introduction
Agreeing how much progress has been made at various stages or a construction project ensures the main parties to the contract are aware of how the programme is proceeding, it can assist in calculating payments due, and it can help identify potential difficulties and avoid delays and disputes.
There are a number of ways in which progress can be assessed and reported.
[edit] Project programmes
Programmes describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time. They will typically identify:
- The start date, completion date and the date the programme was prepared.
- Dates and durations allocated to specific tasks.
- A critical path.
- Tasks which can only be carried out after other tasks have been completed.
- Tasks which can be carried out simultaneously.
- 'Float' within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path).
- The need for specific resources such as plant, services or materials and their lead time.
Programmes do not normally form part of the contract documents, but rather are indicative tools for administering the project and helping to agree progress.
Contracts may require that the contractor provides a master programme for the construction of the works, but again, as this is produced after the execution of the contract, it does not impose any obligation on the contractor beyond those obligations already imposed by the contract documents.
For more information see: Project programme and Contractor's master programme.
[edit] Contractual obligations
Some contracts (such as the New Engineering Contract) may include key dates by which specific milestones or conditions must be met, and the contractor may have a duty to give early warning of anything that may delay the works. The contractor may also be under an obligation to proceed ‘regularly and diligently’ with the works.
[edit] Progress meetings
Progress will typically be assessed at regular construction progress meetings, attended by the contractor and the consultant team, providing an opportunity to:
- Receive progress reports from the contractor (the contractor may also hold progress meetings with sub-contractors and suppliers prior to the construction progress meeting).
- Receive progress reports from the consultant team.
- Receive cost reports from the cost consultant.
- Receive records of sub-contractors and labour on site.
- Receive progress photos.
Progress meetings typically generate a construction progress report for the client.
For more information, see Construction progress meeting and Construction progress report.
[edit] Interim payments.
The Housing Grants, Construction and Regeneration Act stipulates that interim or stage payments are due to any party to a construction contract that has a duration of more than 45 days. Therefore, almost all constructions contain provisions for interim payments.
Contracts should also include clauses that detail:
- The valuation method for payments.
- Criteria under which interim payments will be made.
- Payment timings.
- Administrative rules to which those undertaking the valuation should adhere.
The basis of the valuing interim payments will vary depending on the terms of the contract, but may include:
- Activity schedules assessed in terms of percentage achieved or completion of each activity.
- Milestones reached on a pre-agreed programme.
- Measurement against a bill of quantities.
- Stage payments against calendar dates.
For more information see: Interim valuation.
[edit] Key performance indicators
Key performance indicators (KPIs) are measurable values that can be used to assess how effectively a project, or part of a project are performing. This might include project progress.
Where key performance indicators are to be used on a project, it is important that they are identified in tender documentation and that the regular provision of the information required to assess them is a requirement of the contract. This may be of particular importance where the contract stipulates that the contractor will be rewarded or penalised based on their performance relative to certain indicators.
For more information, see Key performance indicators.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.