Construction progress meeting
During the construction stage, the contract administrator (sometimes referred to in different forms of contract as the 'architect/contract administrator', 'project manager', 'engineer' or 'employer's agent') holds regular (often monthly) construction progress meetings attended by the contractor and if necessary members of the consultant team.
The client, client representative or project manager may also wish to attend these meetings. Construction progress meetings may require decisions to be made and so it is important that they are attended by sufficiently senior individuals if delays are to be avoided.
Construction progress meetings are an opportunity to:
- Receive progress reports from the contractor (the contractor may hold a progress meeting, sometimes called a production meeting, with sub-contractors prior to the construction progress meeting).
- Receive progress reports from the consultant team.
- Receive cost reports from the cost consultant.
- Receive records of sub-contractors and labor on site.
- Receive progress photos (which may be required from the contractor if included in the preliminaries, or may sometimes be commissioned separately by the client).
They are also an opportunity to discuss major issues raised, such as:
- Any special circumstances which may affect the contract at any stage.
- Testing regimes.
- Mock-ups.
- Quality issues.
- Weather reports.
- Issues that may impact on costs.
- Health and safety issues.
- Issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety, etc.).
- Off-site fabrication and off-site payments.
- Earned value analysis.
- Design issues.
- Warranties.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
Meeting minutes should be prepared, with a requirement that any disagreement with the items recorded in the minutes is raised within a pre-defined period (perhaps one week). The progress meetings will also result in the preparation of a construction progress report for the client.
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however, they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
On large projects, the construction manager may hold a daily logistic meeting on site with trade contractor foremen to organise, schedule and co-ordinate on-site shared services such as deliveries and off-loading, hoists and craneage, scaffolding, safety issues, rubbish clearance, etc.
Similar meetings may be held on management contract projects between the management contractor and the works contractors.
[edit] Related articles on Designing Buildings Wiki
- Adapting your technology to the new working normal.
- Client.
- Construction manager.
- Construction progress report.
- Construction stage report.
- Contractor.
- Contract administrator.
- Consultant team.
- Earned value analysis.
- Employer's agent.
- Five steps towards a successful construction project.
- Health and Safety.
- How progress is agreed in construction.
- Management contractor.
- Project programme.
- Progress of construction works.
- Project manager.
- Samples and mock-ups.
- Site meeting.
- Sub contractor.
- Works contractors.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.