Earned value for construction contracts
Earned value analysis (EVA), also known as earned value management (EVM), is a technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.
Typically, EVA is carried out for each of the packages that make up the project. Actual outputs are measured against planned outputs (often on a weekly basis) using the units that individual companies use to price and measure work.
This provides an opportunity to investigate discrepancies and take remedial action where necessary. It also provides a fairly accurate insight into the financial wellbeing of package contractors and provides early warning of a shortage of resources or of an inefficient use of resources.
The key is to measure actual resource against planned resource using the production units by which estimates have been produced in order to price a tender. This can be:
- Hours worked per week.
- Number of workers per week.
- Volume of say, concrete per week per person.
- Units fixed per week per person.
These items can be plotted weekly to alert the user to trends and allow them to investigate causes. Furthermore, it provides an overall general picture of labour productivity for each monitored operation.
Carrying out this sort of analysis requires that project planning is broken down into packages and that tender documentation is drafted to require contractors to supply the information required.
[edit] Related articles on Designing Buildings Wiki
- Benchmarking.
- Contractor.
- Cost monitoring.
- Cost performance index (CPI).
- Identifying the causes of trends in construction labour productivity.
- Key performance indicators.
- Programme consultant.
- Progress of construction works.
- Schedule performance index (SPI).
- Sub-contractor.
- Tender.
- Tender documentation.
[edit] External references
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.