Site meeting
Site meetings are an important part of the successful management of construction projects. Regular site meetings between the different stakeholders on a project can help facilitate better communication and a shared sense of purpose making it more likely that the project is completed successfully. Project failures are often attributed to inadequate management, with a key factor being a lack of proper communication.
Meetings should be regular and formerly scheduled, perhaps on a weekly or monthly basis depending on the parties involved, although the size and complexity of the project may necessitate a more regular schedule. They are used as a means of reporting progress, enabling discussion of any problems or issues, and allowing the proposal of solutions. They provide a good opportunity for two-way discussions of any issues that have arisen or that are anticipated.
Holding meetings on site enables the stakeholders to see progress for themselves (rather than relying on a report for another party), and to look at problem areas, discuss quality issues, assess mock-ups, and so on.
Construction progress meetings are a specific sort of site meeting during which the contract administrator receives progress reports from the contractor and consultant team, cost reports from the cost consultant and other more specific information such as sub-contractor reports, progress photos, and so on.
In order to be able to provide the correct information at construction progress meetings, the contractor may previously hold a progress meeting with sub-contractors sometimes called a production meeting.
Meeting minutes should be prepared, with a requirement that any disagreement with the items recorded in the minutes is raised within a pre-defined period (perhaps one week). Progress meetings may also result in the preparation of a construction progress report for the client.
On construction management projects, the construction manager holds regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. On large projects the construction manager may hold a daily logistic meeting on site with trade contractor foremen to organise, schedule and co-ordinate on-site shared services such as deliveries and off-loading, hoists and cranage, scaffolding, safety issues, rubbish clearance etc.
Similar meetings may be held on management contract projects between the management contractor and the works contractors.
Other meetings held on site might include safety briefings and toolbox talks which are held to ensure that workers properly consider health and safety issues on site.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments