Line of balance (LOB)
Line of balance (LOB) is a management control process used in construction where the project contains blocks of repetitive work activities, such as roads, pipelines, tunnels, railways and high-rise buildings. LOB collects, measures and presents information relating to time, cost and completion, and presents it against a specific plan.
LOB assists project management by:
- Comparing a formal objective against actual progress.
- Examining the extent of any deviations from specific plans, in terms of knock-on effects.
- Identifying in advance problematic areas where corrective action may be required.
- Forecasting future performance.
The LOB technique was created by the Goodyear Company in the early 1940s, before being adopted and developed by the U.S. Navy in the early-1950s. It was subsequently developed for industrial manufacturing and production control, as well as the basic concepts behind planning and scheduling in the construction industry.
An LOB diagram shows the repetitive project work as a single line on a graph. It differs from a bar chart which shows a particular activity’s duration, by showing the rate at which the work has to be undertaken to stay on schedule, as well as the relationship of one trade or process to the subsequent trade or process.
The project timeline is represented along the x-axis of the LOB diagram. The work areas that define the project are represented along the y-axis. This is the starting point for the LOB schedule:
In the figure below, it can be seen that Activity A lasts a 10 weeks. The productivity of A, spread across each of the work areas, is 2 weeks per floor.
If Activity B has a productivity rate of 1 week per floor, then it can begin work at the end of the second week.
As Activity B continues, at the end of the week 4 work can begin on the second floor; at the end of week 6 work can begin on the third floor, and so on. The horizontal red dashed lines represent the breaks in Activity B work, where the workforce is waiting for Activity A to clear the way for them to continue. In this example, starting Activity B as soon as possible will result in a lost productivity of 4 weeks.
The diagram below shows that by delaying the start of Activity B for 4 weeks, the workforce can continue uninterrupted, and hence are more productive. This enables a better understanding of how workforces follow one another through activities.
The advantages of LOB include:
- Allowing a clearer understanding of the amount of work taking place at a certain time in a specific place.
- Resources can be optimised for a large number of repeated work activities.
- As all information is available for each activity, it allows easier cost and time optimisation analysis.
- It is relatively easy to modify, update and change the schedule.
- It allows better management of subcontractors and resources.
- It allows problem areas to be identified in advance.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Advanced manufacturing.
- Block planning.
- Clash avoidance.
- Critical path method.
- Design coordination.
- Gantt chart.
- Key dates.
- Logistics management.
- Milestones.
- Pareto analysis.
- Programme for building design and construction.
- Project manager.
- Resource leveling.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
[edit] External resources
- CPM Tutor - Line of balance
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.