Project crashing
Project crashing is a process that can be used in the management of construction works when the programme is running behind schedule.
Project crashing can be necessary when:
- The programme planning has been inaccurate.
- When there have been unforeseen events which have caused delays, such as defects being discovered.
- Or if the client has requested that the project, or a section of the project, is completed earlier than previously specified, for example if there has been an extension of time, but the client still wishes to achieve the original completion date (this is generally referred to as acceleration).
The aim of crashing is to achieve the maximum decrease in schedule for minimum additional cost. This can be done by:
- Addressing productivity issues being experienced by the current resources and trying to find ways of increasing their efficiency.
- Increasing the assignment of resources on critical path activities. These could be internal resources or subcontracted recources.
- Adopting different techniques. This might include off-site prefabrication, extra scaffolding, temporary weatherproofing and so on.
- Overlapping activities (fast tracking).
- Working longer hours.
- Additional supervision.
- Changes to design or specification (for example standardisation replacing bespoke solutions)
- Reduction in scope (for example transferring work to a separate post-contract agreement for occupational works).
- Early procurement of items.
Many of these strategies will necessarily lead to some additional costs being incurred, or cost uncertainty. Whilst the same number of tasks need to be performed, they are condensed into a shorter period, and so are likely to require more resources. In addition, purchasing costs may be higher due to time pressures, incomplete information and the complexity of managing the interfaces between elements. A greater number of variations are also likely than on a traditional contract.
It is important to be clear whether it is the client or the contractor that will bear these additional costs.
There are several risks attached to project crashing. While resources are typically focused on critical path activities, there is the possibility that non-critical paths will also be affected. Quality, safety and compliance should not be affected as a result of the critical path being crashed. Another risk is that new resources may not be as productive as existing resources, because they may be unfamiliar with the project, the programme and the tasks at hand.
This may require that the size of the contingency is increased.
Project crashing should be resisted if:
- It threatens the integrity of the works, or compromises health and safety.
- It is no longer cost effective to continue.
- It causes another path to become critical.
- Time reduction is no longer realistically achievable.
An alternative to project crashing is fast-track construction, which is a scheduling technique that can be used to compress the overall project schedule. Typically this is decided at the beginning of a project, organising it so that the design and construction phases overlap. This means that that activities normally performed sequential are rescheduled to be performed in parallel or partially in parallel. This will reduce the overall programme, but is likely to increase costs and risks.
For more information, see Fast-track construction.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Constructive acceleration.
- Contractor’s master programme.
- Critical path method.
- Fast-track construction.
- Key performance indicators.
- Milestones.
- Pareto analysis.
- Programme float.
- Project programme.
- Resource leveling.
- Scheduling construction activities.
[edit]
Featured articles and news
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.