Types of costs for buildings
Contents |
[edit] Introduction
The idea of ‘cost’ in relation to buildings is not a simple one, as there are a wide range of different types of cost. This article provides a brief summary of those types, with links to sources of additional information.
[edit] Capital cost
Capital costs are those costs associated with one-off expenditure on the acquisition, construction or enhancement of significant fixed assets including land, buildings and equipment that will be of use or benefit for more than one financial year.
[edit] Construction costs
Construction costs are those costs incurred by the actual construction works themselves, and on some projects may be determined by the value of the contract with the main contractor.
For more information see: Capital costs.
[edit] Building operating costs
Building operating costs are the costs incurred gy the day-to-day operation of the building, which might include; utilities costs, maintenance and repairs, general and administrative expenses and so on.
[edit] Business operating costs
Business operating costs may include building operating costs and also other operating costs such as; rent, wages and so on.
[edit] Life cycle costs
Life cycle costing is an economic assessment of the discounted net present value of life cycle costs, carried out using profiles of current and future costs and benefits. There is increasing emphasis on life cycle costing to ensure all costs are taken into account during the decision-making process, not just those for capital investment.
For more information see: Life cycle costing.
[edit] Whole life costs
Whole life cost. Whole-life costs consider all costs associated with the life of a building, from inception to construction, occupation and operation and disposal.
For more information see: Whole life costs.
[edit] Out-turn costs
Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
For more information see: Out-turn cost.
[edit] Other types of costs
Other types of cost might include:
- Abnormal cost.
- Base cost.
- Baseline costs.
- Cost in use.
- Defined cost.
- Direct cost.
- Disallowed cost.
- Environmental cost.
- Outturn cost.
- Prime cost.
- Project cost.
- Provisional cost.
- Real cost.
- Replacement cost.
- Relevant cost.
- Renewal cost.
- Social cost.
- Sunk cost.
- Target cost.
- Tender cost.
- Total cost.
[edit] Related articles on Designing Buildings
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.