Outturn cost
The term ‘outturn’ or ‘out-turn’ refers to an amount achieved in a certain time, for example, an actual amount produced, or actual sales made. This is in contrast with the amount that might have been predicted or estimated. It is thought to be derived from, or related to, the term ‘turn out’.
The ‘outturn cost’ or ‘out-turn cost’ of a project is its actual construction cost. Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
This meaning of outturn cost is slightly confused by the use of terms such as ‘forecast outturn cost’, ‘estimated outturn cost’ or ‘target outturn cost’ which refer to the cost that is anticipated or should be achieved at the end of the project.
According to the Royal Institution of Chartered Surveyors (RICS), these outturn cost comprises: fixed costs, variable costs, variations, fluctuations and risk allowances.
- Fixed costs are costs that have been pre-calculated and agreed to be paid.
- Variable costs include; provisional sums, provisional quantities, prime cost sums and daywork allowances.
- Variations are alterations in the form of additions, substitutions or omissions from the original scope of works.
- Fluctuations are a way of dealing with inflation on large projects that may last for several years. The contractor is asked to tender based on current prices (prices at an agreed base date) and they are then reimbursed for price changes to specified items over the duration of the project (a fluctuating price).
- Risk allowances are financial allowances for works or services that are unknown in terms of quantity and specification, and are the client’s risk.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines out-turn cost (‘final account’, ‘actual cost’ or ‘cost outcome’) as: ‘The known cost at the end of a project. Generally, it refers to the actual, total construction cost calculated at the end of the project, which includes the effects of any changes made to the design and the impact of any disruption. It may also refer to the costs incurred over a defined period, such as in life cycle cost.’
See also: Final account.
[edit] Related articles on Designing Buildings
- Balance sheet.
- Bill of quantities BOQ.
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Contract conditions.
- Contract sum.
- Cost plans for construction projects.
- Cost reporting.
- Cost Value Reconciliations (CVR).
- Disallowed cost.
- Discounted cash flow.
- Elemental cost plan for design and construction.
- Final account.
- Prime cost sum.
- Quantity surveyor.
- Sunk cost.
- Types of cost.
[edit] External references
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.