Outturn cost
The term ‘outturn’ or ‘out-turn’ refers to an amount achieved in a certain time, for example, an actual amount produced, or actual sales made. This is in contrast with the amount that might have been predicted or estimated. It is thought to be derived from, or related to, the term ‘turn out’.
The ‘outturn cost’ or ‘out-turn cost’ of a project is its actual construction cost. Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
This meaning of outturn cost is slightly confused by the use of terms such as ‘forecast outturn cost’, ‘estimated outturn cost’ or ‘target outturn cost’ which refer to the cost that is anticipated or should be achieved at the end of the project.
According to the Royal Institution of Chartered Surveyors (RICS), these outturn cost comprises: fixed costs, variable costs, variations, fluctuations and risk allowances.
- Fixed costs are costs that have been pre-calculated and agreed to be paid.
- Variable costs include; provisional sums, provisional quantities, prime cost sums and daywork allowances.
- Variations are alterations in the form of additions, substitutions or omissions from the original scope of works.
- Fluctuations are a way of dealing with inflation on large projects that may last for several years. The contractor is asked to tender based on current prices (prices at an agreed base date) and they are then reimbursed for price changes to specified items over the duration of the project (a fluctuating price).
- Risk allowances are financial allowances for works or services that are unknown in terms of quantity and specification, and are the client’s risk.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines out-turn cost (‘final account’, ‘actual cost’ or ‘cost outcome’) as: ‘The known cost at the end of a project. Generally, it refers to the actual, total construction cost calculated at the end of the project, which includes the effects of any changes made to the design and the impact of any disruption. It may also refer to the costs incurred over a defined period, such as in life cycle cost.’
See also: Final account.
[edit] Related articles on Designing Buildings
- Balance sheet.
- Bill of quantities BOQ.
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Contract conditions.
- Contract sum.
- Cost plans for construction projects.
- Cost reporting.
- Cost Value Reconciliations (CVR).
- Disallowed cost.
- Discounted cash flow.
- Elemental cost plan for design and construction.
- Final account.
- Prime cost sum.
- Quantity surveyor.
- Sunk cost.
- Types of cost.
[edit] External references
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Guide to ISO 19650 for Architecture Firms (2026)
A user gives their low down.
A UK training and membership provider for mould remediation professionals.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
Independent NSI and BAFE study exploring how organisations are changing the way they buy fire safety services.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.



















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.