Disruption claims in construction
In construction contracts, the term 'disruption' refers to a loss of productivity due to a hindrance or interruption of the progress of the construction works which reduces the rate of efficiency.
If disruption is caused by the employer, the contractor may have grounds to seek compensation. Disruption, and claims arising to try and recoup losses incurred from it, are common on construction projects, particularly on larger and more complex projects.
The difference between disruption and delay is that the latter relates to lateness rather than productivity, although they can often be related. Delays can cause disruptions, and vice versa. Despite their inter-relation, they require a different approach to assessing claims.
When evaluating claims for delay, the terms of the specific contract are the usual starting point, and evidence is required that certain circumstances caused the delay. The terms of the contract are less useful when evaluating disruption claims. Instead, the contractor must provide reasonable evidence that:
- Progress of the works has been disrupted.
- Which element of the works and which trades have been disrupted, why losses occurred, and so on.
- The disruption incurred additional costs.
- The cause of the disruption constitutes a breach of contract.
Evidence will normally take the form of documented records demonstrating that disruption caused losses. However, this can prove difficult as the contractor can often not detect disruption until after it has occurred. In addition, isolating the loss of productivity to the cause of the disruption can be difficult as it may coincide with several other factors, and the effect of the disruption may be hidden by other issues.
Several methods can be used to estimate loss in relation to disruption, including:
- Measured mile analysis: Compares actual labour performance between two periods – a normal measured mile period and an impacted period.
- Baseline productivity analysis: A more conservative estimate used when an unimpacted section of the works is too difficult to isolate.
- Earned value analysis: Compares the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
NB The term ‘disruption’ can also refer to the impact of new technologies and techniques on an industry. For more information, see Construction is an industry ripe for tech disruption.
Anticipate, react, recover; Resilient infrastructure systems, published by the National Infrastructure Commission in May 2020, defines disruption as: ‘A disturbance which interrupts the usual functioning of an infrastructure system or service, and its impacts.’
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.