Cost reimbursable contract
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee. Option E of the NEC3 Engineering and Construction Contract (ECC) is an example of a cost reimbursable contract.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business). Tendering may proceed based on an outline specification, any drawings and an estimate of costs.
This is a high risk form of contracting for the client as the final cost is not known when the contract is entered into (i.e. there is no contract sum).
The costs for which the contractor is entitled to be reimbursed must be set out very clearly in the contract. This is a complex procedure that needs to be carefully considered, as whilst some direct costs may be relatively straight forward to determine, whilst other ‘shared’ costs, might not.
Direct costs that are clearly attributable to a single project could include:
- Labour.
- Materials.
- Hired plant.
- Sub-contractors.
Other costs that might be spread across more than one project could include:
- Head office costs.
- Staff costs.
- Manufacturing facilities.
- Owned plant.
These costs might be calculated on a pro-rata basis and charged, along with profits as a pre-agreed lump sum, or percentage fee.
In order that the contractor can maintain their cash flow, cost reimbursable contracts may also allow them to charge for liabilities, or for costs that will be incurred before the next interim payment.
Costs are calculated based on the contractor’s accounts and other records, which are made available to the client on an ‘open book’ basis. The client may also monitor activities on site to verify that costs are legitimate (for example, checking whether plant that is being charged is actually being used) and that costs are not excessive. This can become complex where the contractor is thought to be operating inefficiently or incompetently.
The contractor can be incentivised to operate efficiently by the introduction of a target cost. Here, a target cost is agreed at the beginning of the project. At the end of the project the actual cost is compared to the target cost (taking into account any changes that have been agreed). If the actual cost is lower than the target cost, the savings are shared between the parties to the contract on some pre-agreed basis (often a percentage). If the actual cost is higher than the target cost, the additional costs may also be shared.
NB: JCT suggest that a prime cost contract, cost plus and cost reimbursable contract are in fact the same thing. Others consider that a prime cost contract is one in which the cost of works packages (the prime cost) are reimbursed, but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
There are three types of cost reimbursable methods used in the construction industry.
- Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
- Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
- Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Related articles on Designing Buildings
- Admeasurement.
- Contractor.
- Construction contract.
- Contract conditions.
- Contract sum.
- Defined cost.
- Disallowed cost.
- Interim certificate.
- Key dates.
- NEC Option E: Cost reimbursable contract.
- NEC3.
- Open-book accounting.
- Prime cost contract.
- Procurement route.
- Remeasurement.
- Specification.
- Sub-contractors.
- Target cost.
- Tender.
- Time and material contract (T&M).
[edit] External references
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.