NEC Option A: Priced contract with activity schedule
Contents |
[edit] What is NEC?
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It is now in its fourth edition, NEC4.
The Engineering and Construction Contract (ECC) is the most frequently used, and can be adopted on projects such as infrastructure, buildings, highways and process plants. It is used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
[edit] What is option A?
Option A is a priced contract with an activity schedule, which relates to a programme where each activity is allocated a price and interim payments are made against the completion of those activities. The contractor largely bears the risk of carrying out the work at the agreed prices.
The advantage of using an activity schedule is that it simplifies the administration of the interim payment process.
[edit] How are payments calculated?
The activity schedule on these types of project is submitted together with a contract programme as part of the tender.
The activity schedule is a more important document under Option A than under Option C, as it has a significant effect on the contractor’s cash flow by directly effecting the timing and payment amount.
The sum that is due to the contractor in each assessment period is defined as the total of:
- Each group of completed activities (those without defects).
- Each completed activity not in a group.
Only when the whole of an activity is complete does the payment become due to the contractor. There is no provision for part payment.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Conditions of contract.
- Construction contract.
- Contract documents.
- Contractor's working schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- NEC Option F: Management contract.
- NEC3.
- Right to payment.
- Term contract.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.