Material breach
A material breach is a serious violation of a contract that goes to the heart of the agreement, significantly undermining the contract's purpose or the benefits that one party was expected to receive. When a material breach occurs, it typically entitles the non-breaching party to specific legal remedies, including the right to terminate the contract and seek damages.
A minor breach (or non-material breach) is a breach that is less severe and does not fundamentally undermine the contract. The non-breaching party may still seek damages but cannot usually terminate the contract. For example, a minor delay that does not impact the overall project might be considered a non-material breach.
To constitute a material breach the breach must be substantial and not just a minor or trivial failure. It must affect the fundamental aspects of the contract, such as the quality of work, time of completion, or adherence to specified standards. The breach should deprive the non-breaching party of the primary benefits or purpose of the contract. For example, if a contractor fails to meet critical safety standards, it could be considered a material breach because it significantly impacts the project's viability.
A material breach allows the non-breaching party to choose to end the contract, claiming that the breach is so severe that continuing the relationship is untenable. The non-breaching party can seek compensation for losses incurred due to the breach.They might also have the right to suspend their obligations under the contract until the breach is remedied.
Examples of a material breach might include:
- If a contractor fails to meet a key project deadline, leading to significant delays, this might be a material breach, especially if time is of the essence in the contract.
- If a contractor or subcontractor delivers work that does not meet the agreed specifications or industry standards, it could be seen as a material breach, particularly if it compromises the safety or functionality of the construction.
- If a contractor abandons the project without just cause, this would generally be considered a material breach, as it prevents the project from being completed as planned.
- If an employer fails to make critical payments, this could be seen as a material breach, especially if it jeopardises the contractor's ability to continue working.
Whether a breach is considered "material" can be subject to interpretation and often depends on the specific terms of the contract and the circumstances. Courts will look at factors such as the nature of the breach, the consequences, and the intentions of the parties involved.
[edit] Related articles on Designing Buildings
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.