Emerging cost contract
Emerging cost (Time and Materials (T&M)) contracts are most commonly used for rail infrastructure projects.
They are essentially cost reimbursable management contracts for a programme of works and services where the management contractor is paid direct costs identified in an 'estimate of project costs'. They provide for sophisticated management services along with sub-contracting the construction of the works.
However, while there may be target costs and schedules of rates for individual items of the programme of works, with associated incentives and penalties, there is no overall target cost. This means that the final value of the contract may not be known until the contract is complete. This can be useful where setting an overall target cost would restrict the client’s ability to vary the scope of works.
This means the client is accepting many of the financial risks of the project, and must have the expertise and appropriate controls to manage those risks.
Emerging cost contracts provide for value engineering and for the right to terminate if the cost estimate reaches an agreed percentage above the original estimate.
Emerging cost contracts are often applied over a defined period of time. The longer this period of time, the more consideration the contractor is likely to give to long-term performance issues in design and workmanship.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.