Force account work
Force account work, also known as work-by-force account, or time and material work, is a payment method for construction work where there is no existing agreement on cost.
In this case, the works are undertaken with the understanding that the client will pay the contractor according to the actual cost of their labour, materials, and equipment, with an additional percentage for overheads and a mark-up for profit.
It can be used when the contractor and client are unable to agree a unit price or lump sum amount, or if these methods are impracticable, for example, when the quantities and scope of work are unknown at the time of tendering, or for a change order requiring extra, unforeseen work identified after construction has already begun.
Force account work can permit the early start of construction work in critical areas, and can save staff time and overhead costs that would be required for contract package preparation, bidding, evaluation and the award of contracts.
However, it can leave both parties open to unknown costs. The client may not know the quantity, or rates of the works required, and the contractor may agree to very broad terms such as 'all costs' which can leave them struggling to make claims later in the project.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.