Bespoke construction contract
Most construction projects are procured using a standard form of contract that includes standardised, non-negotiated provisions, usually in pre-printed, or digital form. These are sometimes referred to as boilerplate contracts, contracts of adhesion, or take it or leave it contracts.
In the construction industry, there are a number of standard contracts, subcontracts, warranties and appointment agreements published by organisations such as the Joint Contracts Tribunal (JCT), the Royal Institute of British Architects (RIBA), the Institution of Civil Engineers and so on. Such agreements can be effective as they have a track record of being used between parties, and their precise meaning has been tested by case law. Standard form contracts are very often cheaper than bespoke alternatives, familiar to the parties involved (reducing tendering, negotiation and administration costs), and tend to contain fewer unforeseen anomalies.
They can also allow some flexibility, with a wide range of variations, options and schedules that can be tailored to meet the needs of a specific project without altering the construction of the contract clauses.
For more information see: Standard form of contract.
Where this does not give sufficient flexibility, it is possible to amend standard forms of contract. However, this is not always recommended, as there is a complex interaction between many of the terms of standard forms, and modification can change the balance of risk and create legal uncertainty.
For more information see: Modifying clauses in standard forms of construction contract.
Bespoke contracts are specially drafted to suit the specific requirements of a particular project. On some projects, in particular the more complex ones, creating a bespoke contract may be seen as the most efficient means of agreeing terms. Bespoke contracts are also commonly used for very simple supply agreements, where the standard forms may be considered unnecessarily complex and inflexible.
The seminal Latham Report advised against the use of bespoke contracts, but despite this, 24% of respondents to the National Construction Contracts and Law Survey 2012 indicated that they choose to use purpose-written bespoke contracts.
Bespoke contracts may not adequately or fairly make provision for all circumstances, and they are not supported by a history of case law. A large number of legal issues have been created by non-standard bespoke contracts, and they are often costly and time consuming to draft, and disputes can be costly and time consuming to resolve in court.
Bespoke clauses can unintentionally make the meaning of contracts ambiguous, and this can be seized upon by parties in dispute, or seeking additional time or payment. On large projects, there can also be extensive schedules, specifications and other contract documents which may also contain conflicting or ambiguous provisions.
For these and other reasons, contractors tend to be wary of bespoke contracts, with the perception that most clients’ create bespoke contracts to transfer risk.
However, the contractor have little choice but to accept the client’s bespoke contract if they want the work. The commercial judgment should consider:
- How much they want the job in question (perhaps they see it as being a high-profile project that will reap benefits in terms of publicity and future business opportunities).
- How much they are prepared to do for the client in question (perhaps if they have a good working history with the client, or hope that they will offer them more work in the future).
- What the potential risks and costs are.
- How much they can charge to do the job and whether this makes it worth taking on the contractual risks.
Since the contract will govern the relationship between the parties, it is important that it is carefully reviewed and all legal issues considered. This may require seeking legal advice.
English law does not require a particular form to contracts, and so the terms and ultimately the risk allocation is the choice of the parties involved. However, the Housing Grants, Construction and Regeneration Act applies to all contracts for 'construction operations' setting out requirements relating to payment and adjudication. The Scheme for Construction Contracts (England and Wales) Regulations applies when construction contracts do not comply with the Act
[edit] Related articles on Designing Buildings
- Boilerplate
- Breach of contract.
- Causes of construction disputes.
- Construction contract.
- Contract documents.
- Contract negotiation.
- Design and build.
- Essentials of a contract.
- JCT.
- Latham report.
- Levelling the playing field
- Modifying clauses in standard forms of contract.
- Preliminary contracts.
- Procurement route.
- Standard form of contract.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments